在太平哨水电站大坝施工的初期,由于门机没有到货,利用 WK—4型挖掘机改装成10吨履带式起重机,吊运3米~3混凝土罐入仓,完成了一、二期工程中坝基混凝土的浇筑任务。在三期工程中,则改用门机—栈桥吊运混凝土罐入仓的办法,进行坝体混凝土浇筑。为此,在坝的下游侧设置了一座连通两岸的施工栈桥,全桥长315米,共有21跨,每跨15米。在桥上设有三台吉林水工厂生产的10/30吨门座式起重机(简称门机)。
Taipingshan Dam in the initial stage of construction, the door machine did not arrive, the use of WK-4 excavator converted into a 10-ton crawler crane, lifting 3 m ~ 3 concrete tank warehousing, completed the first and second phase of the project The dam foundation concrete pouring mission. In the third phase of the project, instead of using the door machine - trestle lifting concrete tank warehousing approach to dam concrete pouring. To this end, a trestle bridge connecting the two banks of the river is provided on the downstream side of the dam. The full bridge is 315 meters long and has a total of 21 crossings, each spanning 15 meters. In the bridge with three Jilin Water Works production 10/30 tons portal cranes (referred to as door machine).