在海底管道挖沟埋设施工中,除了管道登陆的近岸段采用预挖沟方式挖沟以外,其他海洋段普遍采用海底挖沟机进行后挖沟埋设。在后挖沟施工中,海底管道挖沟机利用高压射流冲射海底泥面形成所需的沟形,采用射流泵将冲射过程中打散的泥沙及时排出工作区域。基于对射流泵设计原理、射流泵的基本方程以及射流泵性能曲线的分析,给出了海底管道挖沟机射流泵的技术参数(最大土方流量、流量比、扬程比、面积比、射流体积流量等)的确定方法及步骤,可为海底管道挖沟机相关参数的确定和主要设备选型提供依据。
In the construction of subsea pipe trenching, except for the trenches dug by the pre-ditching method, the subsea ditches are buried in the other marine sections. In the latter trenching construction, the submarine pipe trencher uses the high-pressure jet to shoot the surface of the sea mud to form the required ditch shape, and the jet pump is used to discharge the sediment dispersed in the punching course out of the work area in time. Based on the design principle of the jet pump, the basic equation of the jet pump and the performance curve of the jet pump, the technical parameters (maximum earth flow, flow ratio, lift ratio, area ratio, jet volume flow Etc.) can be used to determine the relevant parameters of subsea pipeline trenching machine and provide the basis for the selection of major equipment.