由于城市道路交通发展规划,温州叶宅需要原位顶升0.9m,向北平移109m,旋转159°,然后再向东平移21m。结合叶宅房屋整体移位工程,介绍了砖木结构建筑整体迁移工程中结构托换、结构加固、结构称重等各关键环节的构造方案与施工过程,主要包括木柱托换、外墙托换、房屋整体性加固、墙体整体性加固等。
Owing to the planning of urban road traffic development, the leaf house in Wenzhou needs to rise 0.9m in situ, move 109m northwards, rotate 159 °, and then move eastward by 21m. Combined with the overall displacement project of Ye Zhai housing, this paper introduces the construction scheme and construction process of the key links such as structural underpinning, structural reinforcement and structural weighing in the overall relocation project of brick-wood buildings, Change, the overall strengthening of housing, wall consolidation and so on.