论文部分内容阅读
项目背景:辽宁兴城徐大堡核电站位于辽宁省葫芦岛市兴城海滨乡徐大堡村南侧海岸边,厂区东北距兴城市32km、距葫芦岛市46km。核电厂按6台百万千瓦机组规划,总投资为1100亿元,电厂建成后将有助于缓解辽宁中部地区,特别是鞍山、辽阳、营口等地的电力负荷增长的压力。日本福岛核泄漏事件已经过去三年了,但相信公众对核泄漏的“恐惧后遗症”并没有减退,仍然有相当数量的环保组织和民众个人依然对“核电项目”持完全否决的态度。福岛的突发事件令快速跃
Project Background: Xucheng Fortress, Xingcheng City, Liaoning Province is located on the south coast of Xu Dabo Village, Haibin Township, Xingcheng City, Liaoning Province. The northeast of the plant is 32km away from Xingcheng City and 46km away from Huludao City. According to the plan of 6 million kilowatts generating units, the total investment of the NPP will be 110 billion yuan. After the completion of the power plant, it will help relieve the pressure on the power load growth in central Liaoning, especially Anshan, Liaoyang and Yingkou. Japan’s Fukushima nuclear leak has been three years, but I believe the public on the nuclear leak “fear sequelae ” has not diminished, there are still a considerable number of environmental groups and individuals still “nuclear power project ” completely rejected Attitude. Fukushima emergency so fast jump