大型泵房沉井施工,特别是与江河相邻的沉井施工,易出现涌水、涌沙等现象。湘潭市自来水泵房大型沉井施工中采用双液高压化学注浆技术,较好地解决了在动水、流沙中施工的问题。1工程概况湘潭市自来水泵房采用钢筋混凝土沉井,±0.000m标高相当高程41.600m...
The open caisson construction of large pump rooms, especially the construction of caisson adjacent to rivers, is prone to gushing water and sand rushing. Two-fluid high-pressure chemical grouting technology was used in the large-scale open caisson construction of the water pump room in Xiangtan City, which solved the problems in the construction of moving water and sand quickly. 1 Project Overview Xiangtan City Pumping House uses reinforced concrete caisson, ±0.000m elevation is quite high 41.600m...