对长江下游河漫滩地新吹填的松散粉细砂,通过原位监测仪器和跟踪检测,进行了无填料振冲试验、施工技术开发和设计应用。研究了无填料振冲过程中桩周土的超静孔压变化与振冲有效范围,比较了振冲密实前、后桩周土强度变化。针对施工跟踪检测中发现的桩身土局部欠密实问题,分析了缺陷产生原因,提出了解决措施。结果表明,目前规范认为应加填料振冲处理的各种松散粉细砂,只要试验方法得当,及时发现振冲中可能出现的问题并予以解决,吹填粉细砂的无填料振冲密实法是可以大面积应用的。工程试验后提出的振冲设计参数、施工工艺参数和质量控制方法,最终检测显示,工程桩各项指标达到堆场使用要求。
Through the in situ monitoring instruments and tracking test, the loose sand newly filled in the floodplain in the lower reaches of the Yangtze River was tested and the unfilled vibration test, construction technology development and design application were carried out. The change of excess pore pressure and the effective range of vibration around the pile during soilless vibrating process were studied. The changes of soil strength before and after the vibration were compared. In view of the problems of partial densification of pile body and soil found in the construction tracking inspection, the causes of the defects are analyzed and the solutions are put forward. The results show that, as long as the test method is proper, the problems that may appear in the vibrating vibrations are found and solved in time, the unfilled vibrating compacting method Is a large area can be applied. After vibration test design parameters, construction process parameters and quality control methods, the final test showed that the pile of various indicators to meet yard requirements.