荆门热电厂Ⅰ期2台 WG410 t/h锅炉是20世纪70年代生产的燃油机组,1988年对该炉进行“油改煤”改造,并于1989年正式投入运行。由于受场地和费用的限制在保证原有引风机安装位置不变的情况下,在引风机和炉膛之间加装了2套制粉系统和电除尘器。因电除尘器的设计除尘面积小,流通截面小,烟气流速
Jingmen Thermal Power Plant Ⅰ Phase II WG410 t / h boiler is a 1970s-generation fuel unit, the furnace in 1988, “oil to coal” transformation, and officially put into operation in 1989. Due to the site and cost constraints in the original draft fan to ensure that the installation of the same position, in the draft fan and the furnace installed between the two sets of pulverizing system and electrostatic precipitator. Due to the ESP design dust removal area, the flow of small cross-section, flue gas flow rate