昭平台水电站通过对水轮机的允许吸出高度Hs的确定及北干渠流量与各特征点水深关系的计算分析,制定了电站尾水位的调整方案。此方案在实际运行中的实施,提高了机组运行效率,取得了较好的经济效益。
The Zhaopingtai Hydropower Station has formulated the adjustment plan for the tailrace water level through the calculation of the allowable suction height Hs of the turbine and the relationship between the flow of the North Main Canal and the water depth of each characteristic point. The implementation of this program in actual operation has improved the unit operation efficiency and achieved good economic benefits.