山东省天安矿业集团星村煤矿西翼第一部皮带机安装工程中,胶带铺设是整个工程的重要环节,也是整个工程中最难施工的一个环节,15.50斜巷全长近2000m铺设钢丝绳芯胶带,胶带200m/捆,8.8t/200m,且带质较硬,据了解,整个山东省煤矿中我矿西翼运输下山长距离铺设胶带实属首例,经多次研究及在井下施工现场的多次改进,最后制定出了一整套斜巷长距离敷设胶带方案,安全可行,大大降低了工人的劳动强度,消除了安全隐患。顺利地攻克了长距离斜巷铺设胶带这一技术难题。
Shandong Tian’an Mining Group Xingcun Coal Mine West Wing first belt machine installation project, the tape laying is an important part of the entire project, but also the most difficult part of the construction of a link, the entire length of 15.50 inclined nearly 2000m laying of steel cord tape , Tape 200m / bundle, 8.8t / 200m, and with a harder belt, it is understood that the entire coal mine in Shandong Province mine transport west long-distance transport belt down the mountain is the first case, after many studies and in the underground construction site Repeated improvements, and finally developed a set of long-distance roadway laying adhesive tape program, safe and feasible, greatly reducing the labor intensity of workers, eliminating the security risks. Smoothly overcome the long distance of the laying of adhesive tape technology problems.