一、工程概况利港电厂一期工程4×350 MW 机组灰场在距厂区下游3 km 的长江滩地上,西起芦埠港口,东止申港口。该段处于长江江阴段单一微弯河段的凹岸。江面宽4km,江滩宽1~1.5km,江滩高程在0.6~1.5m 间(吴淞高程,下同),枯水期靠岸侧有部分露出水面,汛期漫滩行洪。本期灰场在原江堤北侧三面围堤建
I. General description of the project The ash yard of the 4×350 MW unit of the first phase of Ligang Power Plant is located on the Yangtze River Beach, which is 3 km downstream from the plant area. It starts from Lusheng Port in the west and ends at Shenzhou Port. This section is located on the concave bank of a single microbend section of the Jiangyin section of the Yangtze River. The width of the river is 4km, the width of the riverbank is 1 to 1.5km, and the elevation of the riverbank is between 0.6m and 1.5m (the Wusong elevation, the same below). During the dry season, some of the exposed water surface appears on the beach side, flooding over the flood season. The current ash yard was built on the three levees on the north side of the original river bank.