我省“85”期间重点水利工程之一的定边供水工程于1900年9月正式开工建设以来,工程主体建设速度和质量都取得了可喜的成绩。特别在今年整顿金融紧缩资金的新形势下,全体工程建设者们克服困难团结奋战,使工程进展顺利。截止目前共完成土石方98万m~3,混凝土1.1万m~3,管沟开挖44.5km,混凝土管安装23km,完成省内外永久征地1280亩,临时征地2187亩,拆迁61户。其中单项工程进度是: 1.起点牛家口子至二号隧洞进口输水管道工
Since the “Dingbian Water Supply Project”, one of the key water conservancy projects during the “85” period in our province, was officially started construction in September 1900, the speed and quality of construction of the main project have yielded gratifying results. Particularly in the new situation of rectifying financial tightening funds this year, all construction builders have overcome difficulties and worked together in unity to make the project progress smoothly. Up to now, a total of 980,000 m 3 of earthwork, 11,000 m 3 of concrete, 44.5km of trench excavation and 23km of concrete pipe installation have been completed. Permanent land acquisition inside and outside the province has been completed with 1,280 mu and temporary land acquisition of 2,187 mu with 61 households demolished. The progress of a single project is: 1. Starting point Niujiaokou to No. 2 tunnel import water pipeline workers