黄龙滩水电厂位于鄂西北堵河下游、十堰市黄龙镇以上四公里处。电站总装机容量为2×7.5万千瓦,设计年平均发电量为759亿度。黄龙滩水电站枢纽总体布置为左岸岸边引水式地面厂房。主厂房全长64.18米,宽19.6米,高41米。付厂房在主厂房的上下游侧。电站是1969年4月动工修建的,1972年电站设备陆续到厂进行安装,1974年1月大坝关闸蓄水,5月4日2~#机组投产发电,6
Huanglongtan Hydropower Station is located in the downstream of Du River in northwest Hubei Province, four kilometers above Huanglong Town in Shiyan City. The total installed capacity of the power station is 2 × 75 MW and the designed average annual generating capacity is 75.9 billion kWh. The overall layout of the Huanglongtan Hydropower Station is a water-diversion ground plant on the left bank. The main plant a total length of 64.18 meters, 19.6 meters wide, 41 meters high. Pay the plant on the upstream and downstream side of the main plant. The power station was started construction in April 1969, and the power station equipment was installed in the factory in 1972. In January 1974, the dam closed the impoundment and the 2 ~ # units were put into operation on May 4, 6