介绍了在通州支线工程(北京市南水北调东干渠配套工程)采用PCCP明挖敷设的施工建设中,针对沟槽边坡稳定、管基地层偏软、管道安装、管道回填以及管道内接缝封堵等主要控制难点,采取了有效的处理办法和措施,成功解决了工程难题,确保了工程的质量、安全与进度。通州支线输水管道工程水压试验渗漏量检测结果为0.47 m3/2 h,远小于设计渗漏量3.24 m3/2 h,圆满地完成了通水验收,可为今后类似工程提供借鉴。
This paper introduces the construction of PCCP open cut ditch in the Tongzhou Extension Project (East Nanjing Diversion Project of Beijing South Water Transfer Project). In view of the stability of the trench slope, the soft foundation of the pipe foundation, the pipeline installation, the pipeline backfill and the seams in the pipeline And other major control difficulties, has taken effective measures and measures to successfully solve the engineering problems, to ensure the quality of the project, safety and progress. The result of leakage test of water pressure test of Tongzhou branch pipeline project is 0.47 m3 / 2 h, which is far less than the designed leakage amount of 3.24 m3 / 2 h. It has successfully completed the acceptance of water flow and can provide reference for similar projects in the future.