论文部分内容阅读
概述了棉船洲护岸工程技术试验工程立项的原由,铁塔段整治方案的选择、水上护坎工程与水下护岸工程的设计要点,以及克服开工晚、用复合土工布压盖坎脚抗风浪冲刷、在已抛石的床面上拖拉铺排等施工特点.该试验工程的实施可为崩岸整治的新材料、新技术应用提供重要依据.
The article reviews the reasons for the project of Mianzhu Bay Protection Engineering Test Project, the selection of the scheme for the improvement of the tower section, the design points of the water retaining ridge project and the underwater revetment project, and the countermeasures of overcoming the start of construction, , Tumbled pavement on the bed that has been tossed away, etc. The implementation of this pilot project can provide an important basis for the application of new materials and technologies in bank collapse rectification.