孟加拉迈格纳哈特电厂场地准备项目是中国水电建设集团公司承接的第一个设计+施工的项目,由水电十三局组织施工,总工期为300天,自签定合同之日计算。业主为孟加拉电力发展局,咨询为英国麦克唐纳咨询公司,合同额为14.16亿塔卡,约合2950万美元,资金来自孟加拉政府,全部用当地币塔
The project of site preparation for Meignahat power plant in Bangladesh is the first design + construction project undertaken by China Hydropower Construction Group Corporation. The project is organized by the 13th Bureau of Hydropower and the total construction period is 300 days, calculated from the date of signing the contract. The owner of the Bangladesh Electricity Development Board, consulting for the British Macdonald consulting firm, the contract amount of 1.416 billion taka, or about 29.5 million US dollars, funding from the government of Bangladesh, all in local currency tower