我场全体职工,在迎接1965年生产新高潮中,学习望亭发电厂10号炉快速检修的经验,人人高举毛泽东思想红旗,学习解放军,鼓起革命干劲,展开了8号炉检修的大会战。经过全体指战员的共同努力以及全厂大协作和密切配合,经过奋战,终于以7天多的时间,多快好省地完成了大修任务,比原计划15天缩短一半;除标准项目外,还完成了非标准项目21项,一次启动成功,质量总评价为优,检修项目共124项,其中120项为优,4项为良。安全方面,发生一般未遂一次;共消耗799工,其中标准项目实耗644工,工时比原定额下降50%以上,比历史上
All the staff of our field met the experience of the rapid repair of No. 10 boiler in Wangting Power Plant in welcoming to the new climax of production in 1965. Everyone held high the red flag of Mao Zedong Thought, studied the People’s Liberation Army, and called up the revolutionary drive and launched the assembly of the 8th boiler overhaul. war. Through the joint efforts of all commanders and officers, as well as the cooperation and close cooperation of the entire plant, after more than seven days of hard work, we finally completed the overhaul task more quickly and save half the original 15 days; in addition to the standard project, 21 items of non-standard items were completed, one was successfully launched, and the total quality evaluation was excellent. There were a total of 124 maintenance items, of which 120 were excellent and 4 were good. In terms of safety, a general failure occurred once; a total of 799 workers were consumed, of which 644 were actually used for standard projects, and the number of working hours fell by more than 50% from the original amount.