论文部分内容阅读
结合金溪航电枢纽JX/C03、JX/C14标工程实际,就水电工程结算中临时工程总价承包项目的完工结算、国家政策性调整指令加价的材料的价差补偿、地质原因引起的基础超挖超填的计量与支付等几个合同问题进行了应用分析,简要论述了正确对待和处理这些问题的基本原则和方法,从而提出了水电工程施工合同管理亟需注意的几项工作;对水电工程结算及合同管理具有借鉴作用。
Combined with the actual project of JX / C03 and JX / C14 of Jinxi Hydropower Junction, on the basis of the completion and settlement of the EPC project in the settlement of hydropower projects, the spread compensation of the material with the price increase instructed by the state policy adjustment command and the basic super Digging and overfilling measurement and payment of several contract issues such as application analysis, a brief discussion of the correct treatment and handling of these issues the basic principles and methods, and thus put forward the hydropower project construction contract management should pay attention to several of the work; the hydropower Engineering settlement and contract management have reference.