黄河下游第二期滩区水利建设项目由水利部委托我委承担。截止1994年11月底,第二期滩区水利建设累计完成投资8098万元,共完成土方1067万m~3、石方20万m~3、混凝土方3.6万m~3。上述工程的完成,使黄河下游滩区新增灌溉面积62万亩,新增排水面积7.1万亩,新增淤滩改土面积2.4万亩,新增生产道路150km。
The second phase of the Yellow River beach area water conservancy construction project commissioned by the Ministry of Water Resources commitment. By the end of November 1994, the second phase of water area construction in the beach area had totally invested 80.98 million yuan, totally 10.67 million m 3 of earthwork, 200,000 m 3 of rock and 36,000 m 3 of concrete. The completion of the above project has resulted in the additional irrigation area of 62 million mu in the beach area of the lower reaches of the Yellow River with an additional drainage area of 71,000 mu. The newly-added silt land area of 24,000 mu has been added, and a new production road of 150 km has been added.