温室工程的安装要遵循从下到上、从高到低、从外到内、先地下后地上的原则。温室工程安装顺序为骨架→外遮阳→顶部覆盖→四周围护→湿帘风机→内遮阳→控制→供暖→苗床→给水。1钢骨架的安装温室骨架的安装顺序为主立柱→天沟(含外遮阳立柱)→桁架→辅立柱→横撑→拱杆→檩条→外遮阳横纵撑→斜拉筋。1.1安装准备复验安装定位所用的轴线控制点和测量标高使用的水准点。复验骨架支座及支撑系统的预埋件,其轴线、标高、水平度、预埋螺栓位置等超出允
The installation of greenhouse projects to follow from bottom to top, from high to low, from outside to inside, the first underground after the principle. Greenhouse project installation sequence for the skeleton → outside shade → top cover → surrounded by protection → wet curtain fan → shade → control → heating → seedbed → water supply. 1 steel skeleton installation The greenhouse skeleton installation order main column → gutter (including external sunshade) → truss → auxiliary column → cross brace → arch bar → purlins → outer sunshade diagonal strut → oblique brace. 1.1 Installation Preparation for re-inspection and installation of positioning axis control points used to measure the standard level and the use of elevation. Re-examination of the skeleton bearing and support system embedded parts, the axis, elevation, level, embedded bolt position beyond the allow