矿山由基建移交生产后,迅速使生产达到设计规模(以下简称达产),是生产矿山的重要任务。现对与此有关的问题提出一些看法。一、基建矿山移交生产时应达到的标准 1.完善的井下生产包括提升、运输、通风、压气、供电、供水、排水和废石设施等八大系统。在交工前应该进行试车,并且做到高质量,高标准。有些系统要经过测定,以校验其能力是否满足设计规模的要
After the mine is handed over to production by infrastructure, the production will reach the design scale (hereinafter referred to as production), which is an important task of producing mines. We have some comments on the related issues. I. Criteria to be met during the handover of infrastructure mines 1. Well-developed underground production includes eight systems including upgrading, transportation, ventilation, gasification, electricity supply, water supply, drainage and waste rock facilities. In the delivery of the test should be carried out before, and to achieve high quality, high standards. Some systems have to be tested to verify that their capabilities meet the design requirements