黄河水利工程项目划分工作之我见
马 龙1 陆 伟2 丁兆柱1 张忠华1
( 1.山东垦利黄河河务局; 2.山东东阿黄河河务局, 山东 东阿 252200 )
摘 要:黄河水利工程有其特殊性,决定了项目划分工作复杂性,不像房建工程一样,大同小异。要想正确的进行项目划分工作,必须有依据、有原则、有一定的表现形式,方便资料整理和验收评定,为此,我们根据多年的施工经验对黄河水利工程项目划分的方法作了简要阐述。
关键词:黄河水利工程;项目划分;评定;质量等级
The delineation of the Yellow River water conservancy project
Ma Long1, Lu Wei2, Ding Zhao-zhu1, Zhang Zhong-hua1
(1.Shandong Kenli the Yellow River Engineering Bureau;
2.Shandong Dong-A Yellow River Engineering Bureau, Shandong Dong-A 252200)
Abstract:Yellow River water conservancy project has its particularity, determines the complexity of the project is divided, unlike housing construction in progress, much the same. Project to divide the work in order to correct, you must be based on principles, certain manifestations, documentation and acceptance assessment based on years of construction experience, and we have briefly elaborated on the Yellow River water conservancy project is divided .
Keywords:Yellow River Irrigation Project; project is divided; assessment; quality grade
项目划分工作是黄河水利工程开工前的重要申报材料之一,他对工程内业资料的整理、日常检查验收及评定起着重要作用。2013年—2014年是黄河水利工程施工的高峰期,探讨项目划分工作尤其重要。
1.项目划分的依据
项目划分的依据对于已经批复准备实施的工程项目来说主要是:项目的初步设计、施工方案、概算、黄河防洪工程质量检验与评定规程(试行)。项目划分工作由项目法人(建设单位)组织监理、设计、施工单位参加,在主体工程开工前将项目划分表及说明书面报工程质量监督机构确认。
2.项目划分的原则
黄河水利工程项目划分不像房建工程那样把分项工程、分部工程、单位工程基本定死,黄河工程类型多,项目繁简不一,每个工程都有自己的特点。因此黄河水利工程项目划分的原则:从高层到底层,从宏观到微观。
3.项目划分人员的要求
要想工程项目评价的准确、客观,项目划分工作必须做的合理、细致,这就要求项目划分人员有一定的施工经验,对工程项目的设计、施工总体部署、合同等有个全面的了解,同时也要精通黄河防洪工程质量检验与评定规程,如此才能做到游刃有余,有的放矢,做出的项目划分才具有可操作性。
4.项目划分的表达形式
项目划分的表达形式有2种,一种是黄河工程中常用的表格形式,一种是项目树形式。可以说2种形式各具特色,项目表格形式容量大、层次清楚、项目对应、便于统计,特别是单元工程多时较为明显。项目树形式图文并茂、直观形象、有立体感、便于展示、条理层次清晰,而且应用项目树结构便于以后进行优良品率的分析计算,便于质量评定科学化、标准化,便于统一尺度,达到总体平衡。目前黄河工程以表格形式为主,辅以项目树形式。
5.黄河水利工程项目划分的方法
5.1单位工程的划分
单位工程是指有独立发挥作用或独立施工条件的建筑物。单位工程通常可以是一项独立的工程,也可以是独立工程的一部分,一般按设计、施工部署和便于质量管理等原则来划分单位工程。堤防帮宽工程原则上一个标段为一个单元工程,如果该标段内包含涵闸改建、截渗墙等工程,涵闸改建、截渗墙等可以单独设为一个单位工程。险工改建工程,如果一个标段包含一处险工,该标段可以设为一个单位工程,如果一个标段包括多处险工,每处险工可单独设为一个单位工程。机淤固堤工程,一个标段为一个单位工程。
5.2分部工程的划分
分部工程是指在一个建筑物内组合发挥一种功能的建筑安装工程,是组成单位工程的各个部分。在分部工程中,将其对单位工程的安全、功能或效益起主要控制作用的分部工程称为主要分部工程。分部工程划分时应注意:同一单位工程中,同类型的各个分部工程的工程量不宜相差太大,一般不超过50%;不同建设类型的各个分部工程的投资不宜相差太大,一般不超过50%;每个单位工程中分部工程的数目不宜少于5个。堤防帮宽工程,因断面土方相差不大,一般按长度划分,长度1km左右为一个分部工程,坝身填筑为主要分部工程。险工改建工程按部位和功能进行划分,一般分5个分部工程,坝基处理、坝身填筑、护坡工程、护根工程、附属工程,坝身填筑和
护坡工程为主要分部工程。由于坝岸长度不一,本着“工程量相差不大”原则,坝岸较短的视情况进行合并,以保证工程评定的合理性和准确性。机淤固堤工程,本次机淤固堤工程是黄河标准化工程的一部分,由于原始断面相差大,以“工程量”为尺度进行项目划分,以5万立米左右土方为一个分部工程进行项目划分比较适宜,各分部之间用桩号标示。
5.3单元工程划分
单元工程是项目划分工作的最小“单位”,单元工程有一定的功能,和“工序”有严格的区别,“工序”没有任何功能,他只是完成“单元工程”的一个必不可少的程序而已。堤防帮宽工程中单元工程划分是:堤基清理,沿堤轴线长度100m—500m为一单元工程;堤身填筑,按500m3—2000m3划分一个单元工程;附属工程,每一项(植草、树、排水沟)划分一个单元工程。黄河险工改建工程单元工程划分是:坝基清理,根据险工长度可划分2—3个单元工程。土方填筑,原则上每段坝为一个单元。护根工程、护坡工程、附属工程,根据设计详图上的施工项目分别划分单元工程。土方填筑、护根工程、护坡工程、附属工程划分单元工程时一定要和分部工程划分的段落相对应,这样比较清晰。机淤固堤项目单元工程划分是:在分部工程所划分的堤段内,单元工程有基础清理、淤沙、粘土盖顶、附属工程,共4个。
6.结语
本文主要对黄河近几年来的主要工程项目(堤防帮宽、险工改建、机淤固堤工程)谈了个人一点看法,希望对工程的资料整理、验收和评定有一定的益处。水利工程施工质量等级评定标准是以优良个数占总数的百分率来计算的,工程项目划分是否恰当,对工程质量等级的评定影响很大。
马 龙1 陆 伟2 丁兆柱1 张忠华1
( 1.山东垦利黄河河务局; 2.山东东阿黄河河务局, 山东 东阿 252200 )
摘 要:黄河水利工程有其特殊性,决定了项目划分工作复杂性,不像房建工程一样,大同小异。要想正确的进行项目划分工作,必须有依据、有原则、有一定的表现形式,方便资料整理和验收评定,为此,我们根据多年的施工经验对黄河水利工程项目划分的方法作了简要阐述。
关键词:黄河水利工程;项目划分;评定;质量等级
The delineation of the Yellow River water conservancy project
Ma Long1, Lu Wei2, Ding Zhao-zhu1, Zhang Zhong-hua1
(1.Shandong Kenli the Yellow River Engineering Bureau;
2.Shandong Dong-A Yellow River Engineering Bureau, Shandong Dong-A 252200)
Abstract:Yellow River water conservancy project has its particularity, determines the complexity of the project is divided, unlike housing construction in progress, much the same. Project to divide the work in order to correct, you must be based on principles, certain manifestations, documentation and acceptance assessment based on years of construction experience, and we have briefly elaborated on the Yellow River water conservancy project is divided .
Keywords:Yellow River Irrigation Project; project is divided; assessment; quality grade
项目划分工作是黄河水利工程开工前的重要申报材料之一,他对工程内业资料的整理、日常检查验收及评定起着重要作用。2013年—2014年是黄河水利工程施工的高峰期,探讨项目划分工作尤其重要。
1.项目划分的依据
项目划分的依据对于已经批复准备实施的工程项目来说主要是:项目的初步设计、施工方案、概算、黄河防洪工程质量检验与评定规程(试行)。项目划分工作由项目法人(建设单位)组织监理、设计、施工单位参加,在主体工程开工前将项目划分表及说明书面报工程质量监督机构确认。
2.项目划分的原则
黄河水利工程项目划分不像房建工程那样把分项工程、分部工程、单位工程基本定死,黄河工程类型多,项目繁简不一,每个工程都有自己的特点。因此黄河水利工程项目划分的原则:从高层到底层,从宏观到微观。
3.项目划分人员的要求
要想工程项目评价的准确、客观,项目划分工作必须做的合理、细致,这就要求项目划分人员有一定的施工经验,对工程项目的设计、施工总体部署、合同等有个全面的了解,同时也要精通黄河防洪工程质量检验与评定规程,如此才能做到游刃有余,有的放矢,做出的项目划分才具有可操作性。
4.项目划分的表达形式
项目划分的表达形式有2种,一种是黄河工程中常用的表格形式,一种是项目树形式。可以说2种形式各具特色,项目表格形式容量大、层次清楚、项目对应、便于统计,特别是单元工程多时较为明显。项目树形式图文并茂、直观形象、有立体感、便于展示、条理层次清晰,而且应用项目树结构便于以后进行优良品率的分析计算,便于质量评定科学化、标准化,便于统一尺度,达到总体平衡。目前黄河工程以表格形式为主,辅以项目树形式。
5.黄河水利工程项目划分的方法
5.1单位工程的划分
单位工程是指有独立发挥作用或独立施工条件的建筑物。单位工程通常可以是一项独立的工程,也可以是独立工程的一部分,一般按设计、施工部署和便于质量管理等原则来划分单位工程。堤防帮宽工程原则上一个标段为一个单元工程,如果该标段内包含涵闸改建、截渗墙等工程,涵闸改建、截渗墙等可以单独设为一个单位工程。险工改建工程,如果一个标段包含一处险工,该标段可以设为一个单位工程,如果一个标段包括多处险工,每处险工可单独设为一个单位工程。机淤固堤工程,一个标段为一个单位工程。
5.2分部工程的划分
分部工程是指在一个建筑物内组合发挥一种功能的建筑安装工程,是组成单位工程的各个部分。在分部工程中,将其对单位工程的安全、功能或效益起主要控制作用的分部工程称为主要分部工程。分部工程划分时应注意:同一单位工程中,同类型的各个分部工程的工程量不宜相差太大,一般不超过50%;不同建设类型的各个分部工程的投资不宜相差太大,一般不超过50%;每个单位工程中分部工程的数目不宜少于5个。堤防帮宽工程,因断面土方相差不大,一般按长度划分,长度1km左右为一个分部工程,坝身填筑为主要分部工程。险工改建工程按部位和功能进行划分,一般分5个分部工程,坝基处理、坝身填筑、护坡工程、护根工程、附属工程,坝身填筑和
护坡工程为主要分部工程。由于坝岸长度不一,本着“工程量相差不大”原则,坝岸较短的视情况进行合并,以保证工程评定的合理性和准确性。机淤固堤工程,本次机淤固堤工程是黄河标准化工程的一部分,由于原始断面相差大,以“工程量”为尺度进行项目划分,以5万立米左右土方为一个分部工程进行项目划分比较适宜,各分部之间用桩号标示。
5.3单元工程划分
单元工程是项目划分工作的最小“单位”,单元工程有一定的功能,和“工序”有严格的区别,“工序”没有任何功能,他只是完成“单元工程”的一个必不可少的程序而已。堤防帮宽工程中单元工程划分是:堤基清理,沿堤轴线长度100m—500m为一单元工程;堤身填筑,按500m3—2000m3划分一个单元工程;附属工程,每一项(植草、树、排水沟)划分一个单元工程。黄河险工改建工程单元工程划分是:坝基清理,根据险工长度可划分2—3个单元工程。土方填筑,原则上每段坝为一个单元。护根工程、护坡工程、附属工程,根据设计详图上的施工项目分别划分单元工程。土方填筑、护根工程、护坡工程、附属工程划分单元工程时一定要和分部工程划分的段落相对应,这样比较清晰。机淤固堤项目单元工程划分是:在分部工程所划分的堤段内,单元工程有基础清理、淤沙、粘土盖顶、附属工程,共4个。
6.结语
本文主要对黄河近几年来的主要工程项目(堤防帮宽、险工改建、机淤固堤工程)谈了个人一点看法,希望对工程的资料整理、验收和评定有一定的益处。水利工程施工质量等级评定标准是以优良个数占总数的百分率来计算的,工程项目划分是否恰当,对工程质量等级的评定影响很大。