论文部分内容阅读
为了延长高炉寿命,提高生产效益,在通过了省级技术鉴定的基础上,于1992年6月9~11日在广西壮族自治区柳州钢铁厂召开了高炉灌浆造衬技术推广会。会议由国家科委和冶金部联合主持召开。9个重点企业炼铁厂、14个地方骨干炼铁厂及部分地方铁厂等41个单位66位代表参加了会议。会议听取了柳钢韩奕和作的高炉炉身灌浆造衬护炉技术的研究及推广应用报告,听取了安阳钢铁
In order to extend the life of the blast furnace and improve production efficiency, based on the provincial technical appraisal, a promotion meeting of blast furnace grouting and lining technology was held in Liuzhou Iron and Steel Plant of Guangxi Zhuang Autonomous Region from June 9 to June 1992. The meeting was jointly held by the State Science and Technology Commission and the Ministry of Metallurgy. 66 representatives from 41 key enterprises ironworks, 14 local backbone ironworks and some local ironworks attended the meeting. The meeting listened to Liu Gang, Han Yi and made blast furnace shaft grouting lining protection technology research and promotion application report, heard of Anyang Iron and Steel