我局一条110千伏的輸电工程,去年10月建成投入生产。当时,由于生产急需,在缺乏地线材料、防震錘等器材的情况下采取了“先簡后全”的措施提前送电,滿足了生产急需。今年,根据党的調整、巩固、充实、提高的工业方針,为了确保这条綫路的安全輸电,又对它进行了全面的結尾补套和檢修。这項工作,从今年4月下旬开始到5月上旬結束。由于党的正确领导,职工們发揮了冲天干勁,采取了集中力量保証重点的各项有力措施,在每日停电不超过8小时的条
I have a 110 kilovolt transmission project that was put into production last October. At that time, due to the urgent need of production, in the absence of ground materials, shock-proof hammers and other equipment, the company adopted the “first and foremost” measures to deliver electricity in advance to meet the urgent needs of production. This year, according to the party’s industrial policy of adjustment, consolidation, enrichment, and improvement, in order to ensure the safe transmission of electricity on this route, it also conducted a comprehensive end-of-line repair and maintenance. This work began in late April of this year and ended in early May. Thanks to the party’s correct leadership, the employees have exerted their energy and strength, and they have taken various powerful measures to focus on ensuring the key points. The daily power outage does not exceed 8 hours.