论文部分内容阅读
分析了安康水电厂110kV GIS设备存在的问题并提出对其进行整体改造及增加间隔的可行性,介绍了整体改造的范围、改造施工的质量要求及改造后设备的特点和主要参数。
The existing problems of 110 kV GIS equipment in Ankang Hydropower Plant are analyzed and the feasibility of overall rebuilding and interval increase is proposed. The scope of revamping, the quality requirements of rebuilding and the characteristics and main parameters of reformed equipment are introduced.