论文部分内容阅读
一、概况一九六七年在岗南水电厂安装了从日本富士电机公司引进的一台可逆式抽水蓄能机组及其配套的控制设备,年初开始到货,机组安装的工期(不包括基础部分)为四十六天,于五月十五日投产发电。由于当时的条件不具备,(主变压器和调解池未完),因此是临时发电,水泵抽水试验是拖到后来由电厂做的。接着天津发电设备厂和水控厂等单位接受了试制国产的抽水蓄能机组的任务。分别
I. Overview In 1967, a reversing pumped storage unit and its associated control equipment introduced from Japan’s Fuji Electric Co., Ltd. was installed at Gangnam Hydropower Plant. The arrival of the unit began at the beginning of the year and the installation period of the unit (excluding the basic part ) For 46 days and commissioned to generate electricity on May 15. Since the conditions at that time were not available (the main transformer and the mediation pool were not finished), it was temporary power generation and the pump pumping test was later dragged by the power plant. Then Tianjin Power Plant and water control plants and other units accepted the trial of domestic pumped storage unit mission. respectively