摘要:随着经济的发展,我国近几年建设了一批国家粮食储备库,粮食储备库的主要仓型即为预应力拱板仓型,储备库的屋面则为钢筋混凝土预应力拱板屋架,其跨度主要是21米和24米,宽度一般为1.1米和1.2米,预应力拱板具有跨度大,保温性能良好等优点。本文就结合本人的工作经验对预应力拱板施工技术进行简单的分析,着重以钢筋混凝土预应力拱板屋面结构的施工技术为基础进行论述。
关键字:预应力拱板施工技术屋面结构施工屋盖结构
Abstract: With the development of economy, our country in recent years, the construction of a number of National Grain Reserve. The main type of storage grain reserve is prestressed arch warehouse type, reserve for the roof is reinforced concrete prestressed arch truss, the span is 21 meters and 24 meters, width is generally 1.1 and 1.2 meters, prestressed arch with large span, good insulation performance. In this paper, combined with my work experience make a simple analysis on the construction technology of prestressed arch slab, focusing on the prestressed concrete arch construction technology of roof structure based on.
Keywords: prestressed arch slab roof structure; construction technology; construction; roof structure;
中圖分类号:U443.15+7 文献标识码:A文章编号:
预应力拱板是一种板架合一的屋盖结构构建,期能够在现场预制和现浇,施工的速度快,且能够有良好的保温性能,是一种比较理想的屋面构建,因此被广泛的应用在跨度在21米到24米的粮食储备库拱板工程中。拱板屋架属于空间结构,具有整体性能好、跨度大、重量轻且抗震性能好等优点,能够在不同的地质环境下使用。同时由于其结构形式较为合理,性能比较好,能够很好地发挥其承压能力,能够满足多项功能多要求,具有经济、保温、通风以及隔热等多重功效。下面本文就以21米跨度预应力屋面的拱板施为重点进行详细的论述。
一 钢筋混凝土预应力拱板屋架施工特点分析
钢筋混凝土拱板屋架是由直线形的下弦反槽板、二次抛物线形状的上弦槽板、预制隔板以及钢筋拉杆组成的一种空间结构,其在施工中的特点主要表现在以下几个方面。
首先表现在施工难度大。由于拱板屋架的形状复杂,加之其自重较大,这样在运输和起吊的过程中就会收到一些不可抗力的制约,工厂预制存在一定的困难度;其次,施工过程中对于张拉台座的质量要求较高,但是其重复利用的机会少,不免会出现质量不稳定的情况;再次,由于下弦槽的板肋梁界面较小,配筋密,使得预应力筋就位存在一定的困难。因此说,为了保证没跟配筋都能够产生均衡且有效地预应力,在施加预应力的时候需要保证肋梁和板受力钢筋要实现整体张拉。
二 预应力拱板屋面施工要点分析
在进行施工之前,需要掌握一定的施工要点,才能够保证工程的顺利施工,在施工中需要注意,当在室内搭设钢管排架时,顶撑可以作为拱板底模的支架,在利用标高为7.700米的圈梁作为先张施工的台座,这样能够直接在进行预应力拱板屋架的现浇施工。需要注意,在利用圈梁时需要采取加固的措施,使其不会产生移动的现象。
对于预应力施工的要点分析则需要注意以下几个方面。由于利用标高为7.700米的圈梁作为先张施工的台座,因此说在搭建平台时需要注意,要满足所搭建的平台既能够作为拱板的模板支撑架,又能够作为圈梁的支撑架。在实际施工的过程中需要控制好模板支架以及圈梁等的施工质量,尤其是要对水平顶撑管进行质量监管,确保其能够顶紧屋面的圈梁。在圈梁和水平管接触的地方要保证没有缝隙,以实现轴力的有效传递,否则将会使得圈梁内力和挠度增大,不利于工程的顺利施工和施工质量的保证。
三 预应力屋面拱板施工工艺
预应力拱板屋面是一个空间薄壁板架构建,因此在施工的过程中需要对其外形的大小、构件截面的大小以及施工时预制平台的搭建、拱板模板的制作等的要求都较为严格,同时需要注意,在钢筋装备安装以及混凝土浇筑的过程中也需要严格按照相关的施工工艺进行,这样才能够保证质量。下面本文就从以下几个方面简单的论述预应力屋面拱板施工工艺。
预制平台的搭建
预制平台的搭建是预应力拱板施工的前提基础,预制平台是由扣件式钢管脚手架排架、方木、可调节顶撑以及胶合模板组成的,在搭建的过程中需要保证质量,要合理的利用钢筋混凝土圈梁作为先章预应力的台座。在这个过程中,需要相关的施工者具有丰富的预制平台搭建技术,且搭建的材料要有质量保证,以为今后的预应力屋面拱板施工打下坚实的基础。在实际的搭建中,需要注意,拱板的上弦板的厚度是40毫米,跨度为21米的下弦板的厚度为40毫米,由于搭建的平台的平整度要求较高,因此在搭设之前要明确厚度,使得台面的水平误差尽量控制在5毫米以内,做到误差越小越好。同时,由于预应力张拉时水平顶撑轴力较大,因此说不能够采用旋转扣进行搭建,需要实现对部件进行固定,之后对水平杆进行挤压,最后在第二排将扣件拧紧。同时不能够忽视的是,在预应力张拉之前,圈梁上下的钢筋拉杆必须要保证其处在松弛的状态下。以上几点都是在预制平台搭建过程中需要注意的小技术要点,需要相关的技术人员准确掌握。
(二)钢管排架搭建
钢管排架的搭建也是十分重要的环节,为此需要注意以下几个方面。首先是对支撑系统的基层处理技术方法。支撑系统可以利用钢管架和金属扣进行连接,同时可以搭建脚手架作为模架,在此过程中,需要先按照设计要求进行,等地面基层施工完毕之后,基层的混凝土强度达到设计强度的75%以上,才能够进行脚手架的施工;对于排架的下部,需要铺设50毫米的木方,以增加钢管对地面的摩擦力,相应的减少对于地面基层的压力。平台支架下部要根据拱板的荷载,选择恰当的尺寸部件进行搭建,所有的支撑立杆需要完全应用对接扣件,不能够使用搭接扣件,所有的水平杆和立杆的接头处必须要保证在不同的框格内错开,且错开的长度不能够少于50厘米,各个接头的中心距离节点也不能够大于步距的三分之一。除此之外,还需要注意的是,立杆与水平横杆的连接口需要达到防滑的标准,因此说在保证施工正常进行的同时,还需要加强对零部件的质量监管,保证在钢管排架搭建过程中不因为部件的质量问题而受到影响,从而影响整个预应力屋面拱板的施工进程。
(三)屋面圈梁的施工工艺
混凝土圈梁的施工在整个预应力屋面拱板施工中也具有重要的作用,施工中,混凝土圈梁会受到张拉,此时会发生扭转,因此说为了提高圈梁的抗扭能力,需要将原先的屋面圈梁进行加密处理,增大其抗扭能力,为此,需要在圈梁的两个增加相应的钢筋。需要注意的是,在施工的过程中,为了保证圈梁角落部位的混凝土不被压碎,在外侧的上角需要根据实际情况预埋上一定规格的角钢,而在圈梁外的混凝土天沟底板上则需要增加锚桩,以达到固定锚板的作用。
預应力屋面拱板模型的制作技术
拱板模型的制作需要严格按照制作的工艺和顺序进行,首先在配料上要严格按照要求进行,弧面支模采用九夹板,上弦有24块,下弦分有12块拼装而成,要整块拆模,并将每块都进行编号,集中堆放,便于区分;在放样环节,拱板上弦应为二次抛物线,在预应力屋面拱板施工之前需要按照1:1的比例实地的放出大样之后进行制作,以保证施工的顺利进行;在模板加固环节,因为一般情况下立杆之间的距离为2米,并处于KB板的位置,因此说需要在两个KB板中间的上部水平杆生根,立竖向杆,且需要保证与下部的水平杆相互连接,能够共同传递竖向的荷载,在这个过程中需要注意防止出现侧向位移的现象。需要明确地是,立杆顶标高需要超过底板的标高,这样才能够达到固定肋梁的作用。在接缝处理过程中,需要具有娴熟的拼接工艺,对于模板之间的缝隙需要用海绵填实,之后要用胶带粘牢,不能忽视的是,下底板要同时垫上横木,以防止漏浆现象的出现。
(五)钢筋的安装
当屋面圈梁混凝土达到100%强度之后,才能够张拉预应力筋。需要注意的是,为了保证质量,在张拉之前需要对预应力筋进行抽样检查,防止不合格的预应力筋进入到施工环节,影响整个工程的质量。预应力钢丝采用电动螺杆张拉机进行施工,在每块板状张拉完成之后,要用钢丝应力仪器对张拉力进行测试。最后需要对预应力钢筋锚进行性能试验,检验其是否具有相应的性能,如试验不合格需要尽快采取补救的措施。
混凝土的浇筑施工技术
混凝土的浇筑也是十分重要的环节,在各项检验都合格之后才能进入到混凝土的浇筑环节。由于拱板的屋架属于薄壁构建,因此在浇筑混凝土时需要采用干硬性的混凝土。在浇筑时需要按照一定的顺序进行,先对下弦板进行浇筑,再对上弦板进行浇筑,对于底板和顶板的浇筑,则需要从采取从两端向跨中进行对称浇筑的措施。需要注意的是,混凝土在浇筑的过程中需要一气呵成,不能够在浇筑中留有施工缝。
混凝土浇筑完之后,需要进行养护。混凝土的养护工作能够延长其使用寿命,在保证工程质量方面也具有重要的作用。要进行混凝土养护,可以在混凝土浇筑完成之后,经过振捣压光,可以提前进行覆盖,以防止混凝土表面出现裂缝现象。混凝土初凝之后的养护,则可以用浇水的方法,即向混凝土上浇水,保持湿度,需要注意的是,要保证每天的养护次数要在六次以上,遇到高温天气,应根据实际情况增加浇水养护的次数。对于混凝土的覆盖时间,要达到七天以上,尤其是对下弦的养护更要注意,对其覆盖时间、温度以及适度都要做到细致把握。
(七)竖向支撑和屋面拱板的连接施工
竖向支撑和屋面拱板主要都是由预应力拱板以及墙体顶部标高7.700米的混凝土圈梁连接的,因此说在进行竖向支撑于屋面拱板连接的过程中,需要在标高为7.700米的圈梁混凝土浇筑之前按照相关的设计要求,在恰当的间距位置上预埋件,之后用水准仪找准标高,当屋面拱板安装完成之后进行焊接即可固定住。根据设计规范的要求,在竖向支撑和屋面拱板连接处的焊接点的焊缝高度需要大于5毫米。需要注意的是,如果预埋件出现不平整的现象,则可以加垫铁焊接。在焊接时须注意,内侧不焊接,外侧采取满焊,以保证能够留有足够的变形和位移的控制,增加施工的质量。
(八)模板的拆除施工
模板拆除也需要遵循一定的原则和顺序,需要进行现场同条件的试块的试压强度测验,对于符合设计要求的,经工程施工的技术负责人下发拆除模板通知后,才能够进行拆除。需要注意的是,在模板拆除之前,其混凝土的强度需要符合一定的标准要求,如在拆除肋梁侧模和上弦拱板的模板时,混凝土的强度需要达到1.2MPa,而其底模拆除需要使其强度达到100%,此时才能够拆除模板。
上文中从八个方面论述了预应力拱板屋面施工技术,希望对以后的施工有所帮助,但是需要注意的是,在保证施工技术的同时,需要进行技术创新,探讨符合我国预应力拱板屋面施工的新技术,同时还需要在施工的过程中加强对工程质量的监管,这样才能够促进施工企业的健康发展。
结束语:近几年来,我国的很多地区都在大量的修建粮食储备库,粮食储备库要求要具有保温,隔热、防虫以及防水等性能,且由于其结构的跨度较大,通常情况下使用的是预应力拱板施工技术,采用钢筋混凝土拱板屋面。为了减小拱板屋架的挠度,增加架构性能,需要对拱板屋架的下弦反槽应用先张法预应力的施工,由此可见,预应力拱板施工技术的合理恰当运用,对于拱板屋面的施工具有重要的影响作用。本文就以此为出发点进行论述,在介绍钢筋混凝土拱板屋架施工特点的基础上,对其施工工艺进行简单的论述。希望通过本文的论述,对于今后的工程施工具有一定的帮助作用。
参考文献:
[1] 居镇培 21米预应力拱板施工技术总结 才智,2008年第06期
[2] 李贵 钢筋混凝土预应力拱板施工技术应用 经营管理者,2012年第09期
[3] 北京土木建筑学会 混凝土工程现场施工处理方法与技巧 机械工业出版社,2009-05
[4] 李振起 预应力拱板施工技术 城市建设理论研究,2011年第9期
[5] 晏金洲 预应力拱板屋面结构施工技术 建筑技术,2011年第12期
[6] 蓝宗建 混凝土结构设计原理 东南大学出版社,2008-01
[7] 魏琳 8m高空就地预制先张法21m跨预应力混凝土拱板施工技术 建筑技术,2010年第12期
关键字:预应力拱板施工技术屋面结构施工屋盖结构
Abstract: With the development of economy, our country in recent years, the construction of a number of National Grain Reserve. The main type of storage grain reserve is prestressed arch warehouse type, reserve for the roof is reinforced concrete prestressed arch truss, the span is 21 meters and 24 meters, width is generally 1.1 and 1.2 meters, prestressed arch with large span, good insulation performance. In this paper, combined with my work experience make a simple analysis on the construction technology of prestressed arch slab, focusing on the prestressed concrete arch construction technology of roof structure based on.
Keywords: prestressed arch slab roof structure; construction technology; construction; roof structure;
中圖分类号:U443.15+7 文献标识码:A文章编号:
预应力拱板是一种板架合一的屋盖结构构建,期能够在现场预制和现浇,施工的速度快,且能够有良好的保温性能,是一种比较理想的屋面构建,因此被广泛的应用在跨度在21米到24米的粮食储备库拱板工程中。拱板屋架属于空间结构,具有整体性能好、跨度大、重量轻且抗震性能好等优点,能够在不同的地质环境下使用。同时由于其结构形式较为合理,性能比较好,能够很好地发挥其承压能力,能够满足多项功能多要求,具有经济、保温、通风以及隔热等多重功效。下面本文就以21米跨度预应力屋面的拱板施为重点进行详细的论述。
一 钢筋混凝土预应力拱板屋架施工特点分析
钢筋混凝土拱板屋架是由直线形的下弦反槽板、二次抛物线形状的上弦槽板、预制隔板以及钢筋拉杆组成的一种空间结构,其在施工中的特点主要表现在以下几个方面。
首先表现在施工难度大。由于拱板屋架的形状复杂,加之其自重较大,这样在运输和起吊的过程中就会收到一些不可抗力的制约,工厂预制存在一定的困难度;其次,施工过程中对于张拉台座的质量要求较高,但是其重复利用的机会少,不免会出现质量不稳定的情况;再次,由于下弦槽的板肋梁界面较小,配筋密,使得预应力筋就位存在一定的困难。因此说,为了保证没跟配筋都能够产生均衡且有效地预应力,在施加预应力的时候需要保证肋梁和板受力钢筋要实现整体张拉。
二 预应力拱板屋面施工要点分析
在进行施工之前,需要掌握一定的施工要点,才能够保证工程的顺利施工,在施工中需要注意,当在室内搭设钢管排架时,顶撑可以作为拱板底模的支架,在利用标高为7.700米的圈梁作为先张施工的台座,这样能够直接在进行预应力拱板屋架的现浇施工。需要注意,在利用圈梁时需要采取加固的措施,使其不会产生移动的现象。
对于预应力施工的要点分析则需要注意以下几个方面。由于利用标高为7.700米的圈梁作为先张施工的台座,因此说在搭建平台时需要注意,要满足所搭建的平台既能够作为拱板的模板支撑架,又能够作为圈梁的支撑架。在实际施工的过程中需要控制好模板支架以及圈梁等的施工质量,尤其是要对水平顶撑管进行质量监管,确保其能够顶紧屋面的圈梁。在圈梁和水平管接触的地方要保证没有缝隙,以实现轴力的有效传递,否则将会使得圈梁内力和挠度增大,不利于工程的顺利施工和施工质量的保证。
三 预应力屋面拱板施工工艺
预应力拱板屋面是一个空间薄壁板架构建,因此在施工的过程中需要对其外形的大小、构件截面的大小以及施工时预制平台的搭建、拱板模板的制作等的要求都较为严格,同时需要注意,在钢筋装备安装以及混凝土浇筑的过程中也需要严格按照相关的施工工艺进行,这样才能够保证质量。下面本文就从以下几个方面简单的论述预应力屋面拱板施工工艺。
预制平台的搭建
预制平台的搭建是预应力拱板施工的前提基础,预制平台是由扣件式钢管脚手架排架、方木、可调节顶撑以及胶合模板组成的,在搭建的过程中需要保证质量,要合理的利用钢筋混凝土圈梁作为先章预应力的台座。在这个过程中,需要相关的施工者具有丰富的预制平台搭建技术,且搭建的材料要有质量保证,以为今后的预应力屋面拱板施工打下坚实的基础。在实际的搭建中,需要注意,拱板的上弦板的厚度是40毫米,跨度为21米的下弦板的厚度为40毫米,由于搭建的平台的平整度要求较高,因此在搭设之前要明确厚度,使得台面的水平误差尽量控制在5毫米以内,做到误差越小越好。同时,由于预应力张拉时水平顶撑轴力较大,因此说不能够采用旋转扣进行搭建,需要实现对部件进行固定,之后对水平杆进行挤压,最后在第二排将扣件拧紧。同时不能够忽视的是,在预应力张拉之前,圈梁上下的钢筋拉杆必须要保证其处在松弛的状态下。以上几点都是在预制平台搭建过程中需要注意的小技术要点,需要相关的技术人员准确掌握。
(二)钢管排架搭建
钢管排架的搭建也是十分重要的环节,为此需要注意以下几个方面。首先是对支撑系统的基层处理技术方法。支撑系统可以利用钢管架和金属扣进行连接,同时可以搭建脚手架作为模架,在此过程中,需要先按照设计要求进行,等地面基层施工完毕之后,基层的混凝土强度达到设计强度的75%以上,才能够进行脚手架的施工;对于排架的下部,需要铺设50毫米的木方,以增加钢管对地面的摩擦力,相应的减少对于地面基层的压力。平台支架下部要根据拱板的荷载,选择恰当的尺寸部件进行搭建,所有的支撑立杆需要完全应用对接扣件,不能够使用搭接扣件,所有的水平杆和立杆的接头处必须要保证在不同的框格内错开,且错开的长度不能够少于50厘米,各个接头的中心距离节点也不能够大于步距的三分之一。除此之外,还需要注意的是,立杆与水平横杆的连接口需要达到防滑的标准,因此说在保证施工正常进行的同时,还需要加强对零部件的质量监管,保证在钢管排架搭建过程中不因为部件的质量问题而受到影响,从而影响整个预应力屋面拱板的施工进程。
(三)屋面圈梁的施工工艺
混凝土圈梁的施工在整个预应力屋面拱板施工中也具有重要的作用,施工中,混凝土圈梁会受到张拉,此时会发生扭转,因此说为了提高圈梁的抗扭能力,需要将原先的屋面圈梁进行加密处理,增大其抗扭能力,为此,需要在圈梁的两个增加相应的钢筋。需要注意的是,在施工的过程中,为了保证圈梁角落部位的混凝土不被压碎,在外侧的上角需要根据实际情况预埋上一定规格的角钢,而在圈梁外的混凝土天沟底板上则需要增加锚桩,以达到固定锚板的作用。
預应力屋面拱板模型的制作技术
拱板模型的制作需要严格按照制作的工艺和顺序进行,首先在配料上要严格按照要求进行,弧面支模采用九夹板,上弦有24块,下弦分有12块拼装而成,要整块拆模,并将每块都进行编号,集中堆放,便于区分;在放样环节,拱板上弦应为二次抛物线,在预应力屋面拱板施工之前需要按照1:1的比例实地的放出大样之后进行制作,以保证施工的顺利进行;在模板加固环节,因为一般情况下立杆之间的距离为2米,并处于KB板的位置,因此说需要在两个KB板中间的上部水平杆生根,立竖向杆,且需要保证与下部的水平杆相互连接,能够共同传递竖向的荷载,在这个过程中需要注意防止出现侧向位移的现象。需要明确地是,立杆顶标高需要超过底板的标高,这样才能够达到固定肋梁的作用。在接缝处理过程中,需要具有娴熟的拼接工艺,对于模板之间的缝隙需要用海绵填实,之后要用胶带粘牢,不能忽视的是,下底板要同时垫上横木,以防止漏浆现象的出现。
(五)钢筋的安装
当屋面圈梁混凝土达到100%强度之后,才能够张拉预应力筋。需要注意的是,为了保证质量,在张拉之前需要对预应力筋进行抽样检查,防止不合格的预应力筋进入到施工环节,影响整个工程的质量。预应力钢丝采用电动螺杆张拉机进行施工,在每块板状张拉完成之后,要用钢丝应力仪器对张拉力进行测试。最后需要对预应力钢筋锚进行性能试验,检验其是否具有相应的性能,如试验不合格需要尽快采取补救的措施。
混凝土的浇筑施工技术
混凝土的浇筑也是十分重要的环节,在各项检验都合格之后才能进入到混凝土的浇筑环节。由于拱板的屋架属于薄壁构建,因此在浇筑混凝土时需要采用干硬性的混凝土。在浇筑时需要按照一定的顺序进行,先对下弦板进行浇筑,再对上弦板进行浇筑,对于底板和顶板的浇筑,则需要从采取从两端向跨中进行对称浇筑的措施。需要注意的是,混凝土在浇筑的过程中需要一气呵成,不能够在浇筑中留有施工缝。
混凝土浇筑完之后,需要进行养护。混凝土的养护工作能够延长其使用寿命,在保证工程质量方面也具有重要的作用。要进行混凝土养护,可以在混凝土浇筑完成之后,经过振捣压光,可以提前进行覆盖,以防止混凝土表面出现裂缝现象。混凝土初凝之后的养护,则可以用浇水的方法,即向混凝土上浇水,保持湿度,需要注意的是,要保证每天的养护次数要在六次以上,遇到高温天气,应根据实际情况增加浇水养护的次数。对于混凝土的覆盖时间,要达到七天以上,尤其是对下弦的养护更要注意,对其覆盖时间、温度以及适度都要做到细致把握。
(七)竖向支撑和屋面拱板的连接施工
竖向支撑和屋面拱板主要都是由预应力拱板以及墙体顶部标高7.700米的混凝土圈梁连接的,因此说在进行竖向支撑于屋面拱板连接的过程中,需要在标高为7.700米的圈梁混凝土浇筑之前按照相关的设计要求,在恰当的间距位置上预埋件,之后用水准仪找准标高,当屋面拱板安装完成之后进行焊接即可固定住。根据设计规范的要求,在竖向支撑和屋面拱板连接处的焊接点的焊缝高度需要大于5毫米。需要注意的是,如果预埋件出现不平整的现象,则可以加垫铁焊接。在焊接时须注意,内侧不焊接,外侧采取满焊,以保证能够留有足够的变形和位移的控制,增加施工的质量。
(八)模板的拆除施工
模板拆除也需要遵循一定的原则和顺序,需要进行现场同条件的试块的试压强度测验,对于符合设计要求的,经工程施工的技术负责人下发拆除模板通知后,才能够进行拆除。需要注意的是,在模板拆除之前,其混凝土的强度需要符合一定的标准要求,如在拆除肋梁侧模和上弦拱板的模板时,混凝土的强度需要达到1.2MPa,而其底模拆除需要使其强度达到100%,此时才能够拆除模板。
上文中从八个方面论述了预应力拱板屋面施工技术,希望对以后的施工有所帮助,但是需要注意的是,在保证施工技术的同时,需要进行技术创新,探讨符合我国预应力拱板屋面施工的新技术,同时还需要在施工的过程中加强对工程质量的监管,这样才能够促进施工企业的健康发展。
结束语:近几年来,我国的很多地区都在大量的修建粮食储备库,粮食储备库要求要具有保温,隔热、防虫以及防水等性能,且由于其结构的跨度较大,通常情况下使用的是预应力拱板施工技术,采用钢筋混凝土拱板屋面。为了减小拱板屋架的挠度,增加架构性能,需要对拱板屋架的下弦反槽应用先张法预应力的施工,由此可见,预应力拱板施工技术的合理恰当运用,对于拱板屋面的施工具有重要的影响作用。本文就以此为出发点进行论述,在介绍钢筋混凝土拱板屋架施工特点的基础上,对其施工工艺进行简单的论述。希望通过本文的论述,对于今后的工程施工具有一定的帮助作用。
参考文献:
[1] 居镇培 21米预应力拱板施工技术总结 才智,2008年第06期
[2] 李贵 钢筋混凝土预应力拱板施工技术应用 经营管理者,2012年第09期
[3] 北京土木建筑学会 混凝土工程现场施工处理方法与技巧 机械工业出版社,2009-05
[4] 李振起 预应力拱板施工技术 城市建设理论研究,2011年第9期
[5] 晏金洲 预应力拱板屋面结构施工技术 建筑技术,2011年第12期
[6] 蓝宗建 混凝土结构设计原理 东南大学出版社,2008-01
[7] 魏琳 8m高空就地预制先张法21m跨预应力混凝土拱板施工技术 建筑技术,2010年第12期