新集一矿改扩建工程通过优化设计、优化施工、改革施工管理,仅用14个月时间将矿井生产能力由90万t/a改扩建成300万t/a。此项工程矿建完成一个净径72m、深5025m的立井及装载硐室、-450m马头门、煤仓等;土建完成582m高的两用钢井架、永久提升机房、圆筒仓、装车楼等;机电安装工程完成井筒装备、永久提升机安装调试、井下运输系统安装等。
The new set of mine renovation and expansion project through optimization of design, construction optimization, construction management reform, only 14 months mine capacity from 900,000 t / a to 3 million t / a. The project completed a mining mine shaft diameter of 7 2m, 502 5m depth of the shaft and the load chamber, -450m Ma Tau door, bunker, etc .; civil construction completed 58 2m high steel derrick, permanent upgrading of the engine room, Cylinder silo, loading building, etc .; mechanical and electrical installation works to complete the wellbore equipment, permanent hoist installation and commissioning, underground transportation system installation.