葛洲坝大江电站首台机组启动成功

来源 :动力系统工程 | 被引量 : 0次 | 上传用户:oslo123
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
葛洲坝大江电站第一台125MW水轮发电机组于5月20日23点15分首次启动成功,空载运行2小时后,于21日1点43分正常停机,所测振动、摆度、温升等18项数据均获得令人满意的结果。机械部、水电部有十多个单位的领导和技术人员在现场参加了启动调试工作。启动成功后,工程局、电厂与机械部总代表及哈尔滨电机厂等有关主、辅设 The first 125MW hydroelectric generating set of Gezhouba Dajiang Power Plant was first started successfully at 23:15 on May 20, and after two hours of no-load operation, it was shut down normally at 1:43 on the 21st. The measured vibration, swing, temperature rise All 18 data obtained satisfactory results. Ministry of Machinery, Ministry of MEP has more than a dozen units of leadership and technical personnel on the scene to participate in the start-up and commissioning work. After the successful start, the engineering bureau, the general representative of the power plant and machinery department and the Harbin motor factory and other relevant main and auxiliary facilities
其他文献
分析了单片数控衰减器的衰减原理,设计了一款DC~2 GHz的大衰减量的6 bit数控衰减器。并通过数模混合设计,采用基于GaAs工艺的场效应管驱动器结构将正TTL电平转换为衰减器负的
目前,我国发电设备容量已占世界第六位,但在设备管理方面与国外相比,还有一定差距,其中之一是缺乏设备一生(全过程)的管理,即从设备的设计、制造、安装、运行维护、更新报废
水电部和国家环保局召开的1987年流域水资源保护工作会议现在开幕,参加这次会议的有流域机构负责水资源保护工作的领导同志,各流域水资源保护局(办)负责人以及有关地方和单
据统计,“and”是英语语言中使用频率最高的词汇之一。在有五百万字的字典《The American Heritage Dictionary》中,“and”共出现了133,000次,几乎每一百字就有近三个“and
HB-25型井口射流泵(简称为井口泵),是我局自行设计研制成功的新型射流泵。最大吸程为10.3米,纯排水量为昼夜4~170吨。它的设计以一般射流原理为依据,但为了适用于地面射流抽水的需
根据中国水利电力对外公司与美国哈札工程公司签定的CWEF/0005 MR合同规定,以我院副院长高安泽同志为首的二滩工作组一行五人(成勘院四名,规划院一名)于四月底赴美与哈札工
佳木斯市河道管理处,管理着松花江、黑龙江、牡丹江、汤旺河4条主要江河及10多条重点河流的4072公里河道及1816公里的堤防。党的十一届三中全会以来,他们改革了管理体制,全
河北医科大学第一医院呼吸内科主任杨国明教授等根据多年临床经验,一改过去必须在X线监视及钢丝引导下植入支架的方法,采用丝线把推送器与纤支镜并连方法,经患者鼻孔插入气
古田二级水电站装有两台HL638-LJ-330水轮机,机组额定出力6.5万千瓦,额定转速214.3转/分,电站总装机容量13万千瓦,多年平均发电量4.4亿度。由于当时不能提供完全适合该电站
In this paper, the roles of low velocity and high conductivity body inside the crust in the process of strong earth quake preparation are approached by using th