广东大亚湾核电站核岛土建是由中外合资企业HCCM核电建设合营公司承建、法国“CB”公司和我国核工业总公司华兴建设公司合作施工的。该工程是按照法国的管理模式,运用法国的施工技术,由国内施工。工程按照电子计算机编制的一、二、三级计划网络组织材料、半成品、机具设备和劳动力组合、经过现场合理的协调,工程施工有条不紊,进展十分顺利。一、施工平面布置 1.塔吊的布置核岛大小十九个建筑物和构筑物连成一片,融为一体。占地约14900m~2,施工高峰期布置十一台塔吊,作为现场水平和垂直运输工具。
The nuclear island civil construction of the Guangdong Daya Bay Nuclear Power Station was constructed by the Sino-foreign joint venture HCCM nuclear power construction joint venture company, the French “CB” company and the China National Nuclear Industry Corporation Huaxing Construction Company. The project is based on the French management model, using the French construction technology, from the domestic construction. The project was organized in accordance with the first-, second-, and third-tier plans of the computer network, including the organization of materials, semi-finished products, implement equipment, and labor force, as well as the rational coordination of the project. The construction of the project was well-organized and the progress was very smooth. First, the construction of the layout of the plane 1. Arrangement of the tower crane The size of the nuclear island of nineteen buildings and structures connected into one. Occupying an area of approximately 14900m2, 11 tower cranes are deployed during the peak construction period to serve as on-site horizontal and vertical transportation vehicles.