论文部分内容阅读
石塘水电站位于浙江省云和县瓯江大溪上,是上游正在建设的紧水滩水电站的反调节水库,具有发电和通航效益,装机容量7.8万千瓦,年发电量1.89亿度,初步设计概算总金额为1.775亿元。后在中央领导同志的直接关怀推动下,经过对设计、施工方案的反复修改压缩,使工程投资降到1.4亿元。同时,部党组决定将石塘水电站的施工作为国内公开招标的试点。为加强对试点工作的领导,由部内各有关司局参加,和建设单位、设计单位组成招标领导小组,同时邀请浙江省计委、经委、建设银行等单位参加工作,以共同研究处理招
Shitang Hydropower Station is located in Dasi, Oujiang River, Yunhe County, Zhejiang Province. It is an anti-regulation reservoir of Jishuitan Hydropower Station under construction in the upstream. It has power generation and navigation benefits with an installed capacity of 78,000 kilowatts and an annual generating capacity of 189 million kilowatts. The preliminary design estimate is 177.5 million yuan. After direct leadership by the central leading comrades, the project investment was reduced to 140 million yuan after repeated changes and compaction of design and construction plans. At the same time, the ministry party group decided to Shitang hydropower station construction as a domestic public bidding pilot. In order to strengthen the leadership of the pilot work, relevant departments of the Ministry to participate, and the construction unit, the design unit to form a leading group of tenders, while inviting Zhejiang Provincial Planning Commission, Economic Commission, Construction Bank and other units to participate in work to jointly study and handle