为提高企业管理水平,加快水电建设速度,我局在白山水电站进水口三个闸门井的滑模施工中推行全面质量管理(下简称TQC)的试点工作。该闸门井属于电站的重点项目和控制部位,井筒结构复杂,质量要求高,施工难度大,能否按期或提前完成,将直接影响整个电站蓄水发电的工期。在采用滑模新工艺和实行TQC后,取得了较显著的效果:与常规施工方法比,三个闸门井施工共节约木材650
In order to improve the management level of enterprises and speed up the construction of hydropower, the Bureau conducted the pilot project of Total Quality Management (TQC) in the sliding mode construction of the three gate wells at the inlet of Baishan Hydropower Station. The gate well belongs to the key project and control part of the power station. The wellbore structure is complex, the quality requirements are high, the construction difficulty is large, and whether it can be completed on schedule or in advance will directly affect the construction period of the entire hydropower storage and power generation. In the use of new sliding mode technology and the implementation of TQC, achieved remarkable results: Compared with the conventional construction methods, the construction of a total of three gate wells save timber 650