十一月九日,伍亮副市长召开乙烯工程现场办公会议。参加会议的有市计委、建委、乙烯工程指挥部、广州工程承包总公司等单位和负责同志。会议检查了九月二十二日工作会议纪要的落实情况,听取了广州工程承包公司负责同志关于乙烯工程土(石)方动工后的工作情况与征地有关问题的汇报。会议就广州乙烯工程的前期工作和征地工作中存在的问题,进行了认真的讨论和研究。
On November 9th, Vice Mayor Wu Liang held an ethylene engineering site office meeting. Participated in the meeting are the City Planning Commission, Construction Committee, ethylene engineering headquarters, Guangzhou Engineering Contracting Corporation and other responsible comrades. The meeting examined the implementation of the minutes of the work meeting on September 22. He listened to reports from the responsible comrades of the Guangzhou Engineering Contracting Company on the work situation and land acquisition issues after the ethylene engineering earth (stone) work started. The meeting conducted serious discussions and studies on the pre-existing work of the ethylene project in Guangzhou and the problems existing in land acquisition.