一、包24井生产及卤水处理现状包24井于1988年6月9日投产出地层水,且水量逐渐上升到40m~3/d,采用水罐车运往40km的螺4井回注。由于水处理困难,产气量由15万m~3/d压到8万m~3/d。气井产水继续增加并稳定在96m~3/d,水处理费每月近10万元。气井仍因水处理困难时开时关,使气井不能正常发挥产能。1988年8月至1989年8月,关井时间占总时间的48.9%,少产气4088万m~3。影响矿区生产任务完成和经济效益。
First, the well 24 production and brine treatment package Well 24 in June 9, 1988 put into production of formation water, and the water gradually increased to 40m ~ 3 / d, the use of water tankers transported 40km Spiral 4 well injection. Due to the difficulty of water treatment, gas production was reduced from 150,000 m 3 / d to 80,000 m 3 / d. Gas wells continue to increase water production and stability at 96m ~ 3 / d, water treatment fee of nearly 100,000 yuan per month. Gas wells still open when the water treatment is difficult, so that gas wells can not function properly. From August 1988 to August 1989, the shut-in time accounted for 48.9% of the total time and gas production was 40.88 million m3. Affect the completion of mining production tasks and economic benefits.