为了如实反映三峡工程的各项经济技术指标,也为了合理维护施工单位的经济利益,三联总公司从“岩石坚固系数”的分析人手,较为清晰地揭示了三峡永久船闸地下输水系统石方洞挖期间,工程成本居高不下,施工费用连连超支的主要原因。即工程的实际岩石级别超出了招标文件的描述,对施工进度产生很大影响,并增加了施工过程中钻具、火工材料、钻机等方面的消耗和资金投入。
In order to faithfully reflect the economic and technical indicators of the Three Gorges Project and also to reasonably safeguard the economic interests of the construction units, the Sanlian head office has clearly revealed the underground transmission system stone of the Three Gorges Project from the analytical staff of “Rock Solidity Factor” During the excavation of the square hole, the project cost is so high that the main reason for the excessive construction cost overruns. That is, the actual rock level of the project goes beyond the description of the bidding documents, which has a great impact on the progress of the construction and increases the consumption and capital investment in drilling tools, firework materials and drilling rigs during the construction.