海南省规划建设的重点能源项目——总投资逾65亿元的中海油海南300万吨LNG(液化天然气)项目现场施工已进入关键阶段。截至6月14日,项目总进度(34个月目标计划)已累计完成22.9%,项目总体进展顺利,预计2014年8月建成投产。海南LNG项目接收站站址位于洋浦经济开发区,项目占地57.2公顷,由接收站工程、港口工程及输气管线工程三部分组成,计划2014年8月建成投产。据介绍,海南LNG项目接收站工程建设规模300万吨/年,拟建设2座16万立方米的LNG储罐及其配套的卸料、储存、气化、天然气外输等设施。港口工程
Hainan Province, the key energy project planning and construction - a total investment of 6.5 billion yuan of CNOOC Hainan 3 million tons of LNG (liquefied natural gas) site construction has entered a critical stage. As of June 14, the total progress of the project (34-month target plan) has been completed with a cumulative total of 22.9%. The overall project is progressing well and is expected to be completed and put into operation in August 2014. The site of the receiving station of Hainan LNG Project is located in Yangpu Economic Development Zone. The project covers an area of 57.2 hectares and is composed of receiving station project, port project and gas transmission pipeline project. It is planned to be completed and put into operation in August 2014. According to reports, Hainan LNG project receiving station construction scale of 3 million tons / year, proposed the construction of 160,000 cubic meters of LNG storage tanks and supporting the unloading, storage, gasification, natural gas and other facilities. Port Engineering