结合现场实测数据,对叠交隧道短期内二次穿越施工参数的设定、地面和先建隧道的变形规律进行了研究。结果表明:盾构在近距离上穿施工时,土仓压力、注浆压力及注浆量较常规段要大,推进速度的设定要综合考虑盾构机出土效率、注浆效果,并非越慢越好。本工程穿越施工时的设定值为40mm/min,现场实测发现变形符合设计要求。短期内二次穿越施工引起叠交区地面变形量值较常规段要大,本工程后建隧道上、下行线穿越施工引起叠交区域内最大竖向变形量分别为+7.4mm和-17.9mm,因此该区域是变形控制的重点。已建隧道的变形既包含自身的固结变形又包括后建隧道施工的扰动影响,实测变形为两者的综合,规律性不明显。
Based on the field data, the setting of secondary crossing construction parameters of the overlapped tunnels and the deformation of the ground and the first tunnel were studied. The results show that when the shield is worn in close distance, the pressure of silo, the pressure of grouting and the amount of grouting are larger than that of the conventional section. The setting of the propulsion speed must consider the unearthed efficiency and grouting effect of shield machine, Slow is better. The project through the construction of the set value of 40mm / min, the field measured deformation found to meet the design requirements. In the short term, the amount of ground deformation caused by the secondary crossing construction is larger than that in the conventional section. The maximum vertical deformation in the overlapping area caused by the construction of tunnels across the tunnel after the construction of this project is respectively + 7.4mm and -17.9mm , So the area is the focus of deformation control. The deformation of the built tunnel not only includes its own consolidation deformation but also includes the disturbance of the post-construction tunnel construction. The measured deformation is the combination of the two, and the regularity is not obvious.