摘要:忽视设计阶段工程造价的控制是产生基建投资失控现象的一个很主要的原因。工程设计是建设项目进行全面规划和具体描述实施意图的过程,是工程建设的灵魂,是处理技术与经济关系的关键环节,是确定与控制工程造价的重要因素。因此,必须从推行设计招标制度、推行设计监理制度、推广标准设计、实行设计质量奖罚制度、实施限额设计、加强施工图的审核工作和提高设计质量等方面入手,把控制造价的观念渗透到各项设计中,将工程造价控制工作推向一个新的里程碑。
关健词:设计阶段 ,造价控制, 控制措施
Abstract: the neglect of engineering cost control design phase is to produce infrastructure investment out of control of the phenomenon of a very main reason. Engineering design is a construction project planning and comprehensive description implement the intentions of the process, is the soul of the construction of engineering, technology and economy is to deal with the relationship between the key link, is sure to control the engineering cost and the important factors. Therefore, we must push from bidding for the design of system design, the implementation of the supervision system, the promotion of standard design, the design quality award system, carrying out quota design and construction drawing, and strengthening the audit work and improve the design quality and teaching, the control cost penetrate to the design, engineering cost control to a new milestone.
Key words: the design phase, cost control, the control measures
中图分类号:TU723.3文献标识码:A 文章编号:
工程造价控制是工程建设管理工作的重要组成部分,如何合理确定和有效控制工程投资,是工程项目建设的一大难题。多年来,随着招投标制度的实施和定額的不断完善,已收到了比较好的效果,但在商品经济高速发展的今天,基本建设投资失控的现象依然不同程度的存在,“三超”现象普遍存在,现在对于建设工程造价的控制,主要或者说绝大部分是在建设实施(施工)阶段,一般只注重施工预算、结算而忽视实施前的造价控制;只注重施工而忽视设计;只注重砍价和压价而忽视了科学合理的定价;只注重造价控制的形式而忽视其实质--是否是真正意义上的控制。其结果是事倍功半,造价控制效果不理想。严重困扰着建设工程投资的管理,就其超支的原因很多,但忽视设计阶段工程造价的控制是一个很重要的因素。
一、 加强设计阶段工程造价管理的重要性:
应该说,控制造价必须从投资决策阶段开始抓起,这才是从龙头抓起,但是,由于投资决策时连方案都没有,要确定准投资额也确实不那么容易,尤其是民用建筑变化比较大,虽然是同一类建筑,可是由于建筑方案不同、设计标准不同,所选用的材料设备不同,所采用的结构形式不同(当然施工地点、方法、管理的不同也是造成造价不一样的重要原因),致使它们的造价也是千差万别的,因此,即使是建筑类别相同,但也很难有相同的工程造价。
1、 设计阶段控制造价是花小钱办大事
只有在设计阶段进行造价控制,才能实现真正意义上的控制造价。据西方一些国家分析,设计费一般只相当于建设工程全寿命费用的百分之一以下,但正是这少于百分之一的费用对工程造价的影响度占到百分之七十五以上。所谓建设工程全寿命费用包括工程造价和工程交付使用后的经常开支费用(含经营费用、日常维护修理费用、使用期内大修理和局部更新费用)以及该项目使用期满后的报废拆除费用等。
该阶段的造价控制不只是表面意义上的控制估算、概算、预算,而其实际意义在于通过控制造价,达到提高设计质量、降低工程成本、取得最佳经济效益和社会效益的目的,即取得真正意义上的控制造价。
2、 设计阶段控制造价充分体现了事前控制的思想。
由于设计阶段毕竟是纸上谈兵,建设项目还没有开始施工,因此,是调整还是改动都比较容易,而施工阶段改起来就麻烦多了。根据有关资料显示,项目在规划设计阶段,对其工程整个投资影响最大,可以达到90%以上,规划设计水平的优劣,对工程实物的投资、工程进度和建筑质量有着很重要的影响。只有在设计工作没有完成,设计图纸未交付使用之前把好工程造价管理的第一关,才能为总体工程造价控制打好基础,有资料研究表明:在初步设计阶段,影响工程造价的可能性为75%—95%;在技术设计阶段,影响工程造价的可能性为35%—75%;在施工图设计阶段,影响工程造价的可能性为25%—35%;而到了工程实施阶段,影响工程投资的可能性已经只有5%—25%。由此看来,控制工程造价的关键在于设计阶段。
3、设计阶段控制造价既是必须的又是行之有效的,同时在此阶段控制造价也能起到事半功倍的效果。
长期以来,我国普遍忽视工程建设项目设计阶段的造价控制,结果出现有些设计粗糙,初步设计深度不够,设计概算质量不高,有些项目甚至不要概算,概算审批走形式,造成三超现象(概算超估算,预算超概算,结算超预算)严重。业主(建设单位)往往把控制工程造价的主要精力放在施工阶段--审核施工图预算、合理结算建安工程价款,算细帐。这样做尽管也有效果,但毕竟是"亡羊补牢",事倍功半。要有效地控制建设工程造价,就必须把控制重点转到设计阶段这一关键阶段上来,未雨绸缪,以取得事半功倍的效果。
二、 设计阶段工程造价控制的主要措施:
1、设计招标制度的推行:
设计招标制度的推行为建设单位在规划设计阶段提高设计质量,进行投资控制提供了契机。在设计招标过程中,建设单位就有权对投标方案的合理性、经济性进行评估和比较。在满足设计任务书的要求下,把设计的经济性也纳入评标条件。当前,一般评标所邀请的多为工程方面的专家,而懂建筑专业知识的经济类专家却很少参与,这就容易造成评标质量的偏差。所以,在确定中标方案后,建设单位仍有必要汇集开发、预算、工程管理和营销部门的专业人员,共同对中标方案再次提出优化意见,进一步提高设计的经济性和合理性。
设计是工程建设的龙头,当一份施工图付诸于施工时,就决定了工程本质和工程造价的基础。一个工程在造价上是否合理,是浪费还是节约,在设计阶段已大体定型。由设计不当造成的浪费,其影响之大是人们难以预料的。目前设计部门普遍存在“重设计、轻经济”的观念。设计概预算人员机械地按照设计图纸编制概预算,用经济来影响设计,优化设计,衡量、评价设计方案的优秀程序以及投资的使用效果只能停留在口头。设计人员在设计时只负技术责任,不负经济责任。在方案设计上很多单位都能做到二个以上方案进行比较,但却很少考虑在经济上是否合理,出现了"多用钢筋,少动脑筋"的现象。特别在竞争激烈的情况下,设计人员为了满足建设单位的要求,为了赶进度,施工图设计深度不够,甚至有些项目(如装修部分)出现做法与选型交代不清,使设计预算与实际造价出现严重偏差,预算文件不完整。因此,推行设计招标,引进竞争机制,迫使竞争者对建设项目的有关规模、工艺流程、功能方案、设备选型、投资控制等作全面周密的分析、比较,树立良好的经济意识,重视建设项目的投资效果,用最经济合理的方案设计参加竞赛。而建设单位通过应用价值工程理论等对设计方案进行竞选比较、技术经济分析,从中选出技术上先进、经济上合理、既能满足功能和工艺要求,又能降低工程造价的技术方案。
为鼓励和促进设计人员做好方案选择,把竞争机制引入设计部门,这样才能激发设计者以最优化的设计,最合理的造价,赢得市场,从而有效地控制造价。
2、 推行设计监理制度
目前,政府主管部门一直未出台设计监理机制,方案设计、消防设计、煤气等审查部门各管一部分,不利于价格控制。虽然我国推行建设监理制,但设计的监理工作还未强制执行。让一部分有经验的监理人员参与到设计阶段来,在一些开发单位已经实施,并取得了效果。推行设计监理,从项目可行性研究阶段就参与进去,协助开发商调研、考察、立项,论证方案的可行性并提出合理性建议。实行设计监理,可以减少设计过程中可能存在的缺陷与失误,提高设计质量,有效控制工程价格。
3、 推广标准设计:
即采用国家、省、市级各专业部属的标准通用设计,既可以缩短设计周期,还由于采用标准构件,可以在预制厂采用定型工艺,组织成批均衡生产,既能提高劳动生产率,有利于降低生产成本,并可加快施工速度,缩短整个建设周期。因而,采用标准设计,也是降低造价的一个方法。
4、 改变设计取费办法,实行设计质量的奖罚制度
现行的设计费计算方法,不论是按投资规模计价,还是按平方米收费,没有任何经济责任,不管工程设计的质量好坏,不论投资超不超预算,甚至不管建设项目有没有实施,设计人员有没有到现场服务,只要出了图纸,就得给设计费。这种计费办法助长了设计单位只重视技术性,忽视科学性、经济性的观念。实际工作中经常会碰到设计过于保守或设计功能没有达到最优或在施工过程中随意变更,致使工程造价居高不下和决算价大大超出原概算,对建筑业的正常发展造成不良的影响。因此,应对现行设计费的计费方法和审核办法进行改革,建立激励机制。试行在原设计计费的基础上,对因设计而节约的投资,按节约部分给予提成奖励;因设计变更而增加的投资也按增加部分扣除一定比例的设计费,实行优质优价的计费办法,这样将有利于激励设计人员精益求精地进行设计,加强设计人员的经济意识,时刻考虑如何降低造价,把控制工程造价观念渗透到各项设计和施工技术措施之中。
5、 实施限额设计:
所谓限额设计,就是按照批准的设计任务书和投资估算来控制初步设计,按照批准的初步设计总概算控制施工图设计,同时各专业在保证达到使用功能的前提下,按分配的投资限额控制设计,严格控制技术和施工图设计的不合理变更,保证总投资额不被突破。限额设计并不是一味地考虑节约投资,也决不是简单地将投资砍一刀,而是包含了尊重科学,尊重实际,实事求是,精心设计和保证设计科学性的实际内容。投资分解和工程量控制是实行限额设计的有效途径和主要方法。将"画了算"变为"算着画",时刻想着"笔下一条线,投资千万"。
要求设计单位在工程设计中推行限额设计。凡是能进行定量分析的设计内容,均要通过计算,将技术与经济相结合,用数据说话,在设计时应充分考虑施工的可能性和经济性,要和技术水平和管理水平相适应,要特别注意选用建筑材料或设备的经济性,盡量不用那些技术未过关、质量无保证、采购困难、运费昂贵、施工复杂或依赖进口的材料和设备;要尽量搞标准化和系列化的设计;各专业设计要遵循建筑模数、建筑标准、设计规范、技术规定等进行设计;要保证在项目设计达到使用功能的前提下,按分配的投资限额控制设计,严格控制技术设计和施工图设计的不合理变更,保证总投资额不被突破。
6、 加强施工图的审核工作。
这是我们以往工作中的薄弱环节。审核的内容不仅仅是各专业图纸的交圈,更重要的是检验设计图纸与投资决策中相关内容的吻合。由技术部门负责审核图纸的设计范围、结构水平、建筑标准等内容;由造价管理部门负责审核设计概算与施工图纸的一致性,设计概算与投资估算的协调性,如有超概算的项目,应与各部门之间全力配合,将突破投资的内容进行调整,为工程施工阶段的投资控制打下坚实的基础。
7、提高设计质量:
设计阶段是项目即将实施而未实施的阶段,为了避免施工阶段不必要的修改,避免设计洽商费用的增加,从而增加工程造价,应把设计做细、做深入。因为,设计的每一笔每一线都是需要投资来实现,所以在没有开工之前,把好设计关尤为重要,一旦设计阶段造价失控,就必将给施工阶段的造价控制将带来很大的负面影响。现在,有的业主往往为了赶周期、压低设计费,设计阶段的造价没有控制好,方案估算、设计概算没有或者有也不符合规定、质量不高,结果到施工阶段给造价控制造成困难。前面已提到设计费一般只相当于建设工程全寿命费用的百分之一以下,但对工程造价的影响度却占到百分之七十五以上。
三 结语
总之,设计阶段的造价控制虽然并不那么轻松,但它确是真正体现了事前控制的思想,确实能起到事半功倍的效果,达到花小钱办大事的目的,只有当业主(建设单位)真正把控制造价的关键阶段确立在设计阶段时,才能收到投资省、进度快、质量好的效果。通过技术比较、经济分析和效果评价,正确处理技术先进与经济合理两者之间的对立统一关系,力求在技术先进条件下的经济合理,在经济合理基础上的技术先进,把控制工程造价的观念渗透到各项设计和施工技术措施中,将工程造价控制工作推向一个新的里程碑。
注:文章内所有公式及图表请以PDF形式查看。
关健词:设计阶段 ,造价控制, 控制措施
Abstract: the neglect of engineering cost control design phase is to produce infrastructure investment out of control of the phenomenon of a very main reason. Engineering design is a construction project planning and comprehensive description implement the intentions of the process, is the soul of the construction of engineering, technology and economy is to deal with the relationship between the key link, is sure to control the engineering cost and the important factors. Therefore, we must push from bidding for the design of system design, the implementation of the supervision system, the promotion of standard design, the design quality award system, carrying out quota design and construction drawing, and strengthening the audit work and improve the design quality and teaching, the control cost penetrate to the design, engineering cost control to a new milestone.
Key words: the design phase, cost control, the control measures
中图分类号:TU723.3文献标识码:A 文章编号:
工程造价控制是工程建设管理工作的重要组成部分,如何合理确定和有效控制工程投资,是工程项目建设的一大难题。多年来,随着招投标制度的实施和定額的不断完善,已收到了比较好的效果,但在商品经济高速发展的今天,基本建设投资失控的现象依然不同程度的存在,“三超”现象普遍存在,现在对于建设工程造价的控制,主要或者说绝大部分是在建设实施(施工)阶段,一般只注重施工预算、结算而忽视实施前的造价控制;只注重施工而忽视设计;只注重砍价和压价而忽视了科学合理的定价;只注重造价控制的形式而忽视其实质--是否是真正意义上的控制。其结果是事倍功半,造价控制效果不理想。严重困扰着建设工程投资的管理,就其超支的原因很多,但忽视设计阶段工程造价的控制是一个很重要的因素。
一、 加强设计阶段工程造价管理的重要性:
应该说,控制造价必须从投资决策阶段开始抓起,这才是从龙头抓起,但是,由于投资决策时连方案都没有,要确定准投资额也确实不那么容易,尤其是民用建筑变化比较大,虽然是同一类建筑,可是由于建筑方案不同、设计标准不同,所选用的材料设备不同,所采用的结构形式不同(当然施工地点、方法、管理的不同也是造成造价不一样的重要原因),致使它们的造价也是千差万别的,因此,即使是建筑类别相同,但也很难有相同的工程造价。
1、 设计阶段控制造价是花小钱办大事
只有在设计阶段进行造价控制,才能实现真正意义上的控制造价。据西方一些国家分析,设计费一般只相当于建设工程全寿命费用的百分之一以下,但正是这少于百分之一的费用对工程造价的影响度占到百分之七十五以上。所谓建设工程全寿命费用包括工程造价和工程交付使用后的经常开支费用(含经营费用、日常维护修理费用、使用期内大修理和局部更新费用)以及该项目使用期满后的报废拆除费用等。
该阶段的造价控制不只是表面意义上的控制估算、概算、预算,而其实际意义在于通过控制造价,达到提高设计质量、降低工程成本、取得最佳经济效益和社会效益的目的,即取得真正意义上的控制造价。
2、 设计阶段控制造价充分体现了事前控制的思想。
由于设计阶段毕竟是纸上谈兵,建设项目还没有开始施工,因此,是调整还是改动都比较容易,而施工阶段改起来就麻烦多了。根据有关资料显示,项目在规划设计阶段,对其工程整个投资影响最大,可以达到90%以上,规划设计水平的优劣,对工程实物的投资、工程进度和建筑质量有着很重要的影响。只有在设计工作没有完成,设计图纸未交付使用之前把好工程造价管理的第一关,才能为总体工程造价控制打好基础,有资料研究表明:在初步设计阶段,影响工程造价的可能性为75%—95%;在技术设计阶段,影响工程造价的可能性为35%—75%;在施工图设计阶段,影响工程造价的可能性为25%—35%;而到了工程实施阶段,影响工程投资的可能性已经只有5%—25%。由此看来,控制工程造价的关键在于设计阶段。
3、设计阶段控制造价既是必须的又是行之有效的,同时在此阶段控制造价也能起到事半功倍的效果。
长期以来,我国普遍忽视工程建设项目设计阶段的造价控制,结果出现有些设计粗糙,初步设计深度不够,设计概算质量不高,有些项目甚至不要概算,概算审批走形式,造成三超现象(概算超估算,预算超概算,结算超预算)严重。业主(建设单位)往往把控制工程造价的主要精力放在施工阶段--审核施工图预算、合理结算建安工程价款,算细帐。这样做尽管也有效果,但毕竟是"亡羊补牢",事倍功半。要有效地控制建设工程造价,就必须把控制重点转到设计阶段这一关键阶段上来,未雨绸缪,以取得事半功倍的效果。
二、 设计阶段工程造价控制的主要措施:
1、设计招标制度的推行:
设计招标制度的推行为建设单位在规划设计阶段提高设计质量,进行投资控制提供了契机。在设计招标过程中,建设单位就有权对投标方案的合理性、经济性进行评估和比较。在满足设计任务书的要求下,把设计的经济性也纳入评标条件。当前,一般评标所邀请的多为工程方面的专家,而懂建筑专业知识的经济类专家却很少参与,这就容易造成评标质量的偏差。所以,在确定中标方案后,建设单位仍有必要汇集开发、预算、工程管理和营销部门的专业人员,共同对中标方案再次提出优化意见,进一步提高设计的经济性和合理性。
设计是工程建设的龙头,当一份施工图付诸于施工时,就决定了工程本质和工程造价的基础。一个工程在造价上是否合理,是浪费还是节约,在设计阶段已大体定型。由设计不当造成的浪费,其影响之大是人们难以预料的。目前设计部门普遍存在“重设计、轻经济”的观念。设计概预算人员机械地按照设计图纸编制概预算,用经济来影响设计,优化设计,衡量、评价设计方案的优秀程序以及投资的使用效果只能停留在口头。设计人员在设计时只负技术责任,不负经济责任。在方案设计上很多单位都能做到二个以上方案进行比较,但却很少考虑在经济上是否合理,出现了"多用钢筋,少动脑筋"的现象。特别在竞争激烈的情况下,设计人员为了满足建设单位的要求,为了赶进度,施工图设计深度不够,甚至有些项目(如装修部分)出现做法与选型交代不清,使设计预算与实际造价出现严重偏差,预算文件不完整。因此,推行设计招标,引进竞争机制,迫使竞争者对建设项目的有关规模、工艺流程、功能方案、设备选型、投资控制等作全面周密的分析、比较,树立良好的经济意识,重视建设项目的投资效果,用最经济合理的方案设计参加竞赛。而建设单位通过应用价值工程理论等对设计方案进行竞选比较、技术经济分析,从中选出技术上先进、经济上合理、既能满足功能和工艺要求,又能降低工程造价的技术方案。
为鼓励和促进设计人员做好方案选择,把竞争机制引入设计部门,这样才能激发设计者以最优化的设计,最合理的造价,赢得市场,从而有效地控制造价。
2、 推行设计监理制度
目前,政府主管部门一直未出台设计监理机制,方案设计、消防设计、煤气等审查部门各管一部分,不利于价格控制。虽然我国推行建设监理制,但设计的监理工作还未强制执行。让一部分有经验的监理人员参与到设计阶段来,在一些开发单位已经实施,并取得了效果。推行设计监理,从项目可行性研究阶段就参与进去,协助开发商调研、考察、立项,论证方案的可行性并提出合理性建议。实行设计监理,可以减少设计过程中可能存在的缺陷与失误,提高设计质量,有效控制工程价格。
3、 推广标准设计:
即采用国家、省、市级各专业部属的标准通用设计,既可以缩短设计周期,还由于采用标准构件,可以在预制厂采用定型工艺,组织成批均衡生产,既能提高劳动生产率,有利于降低生产成本,并可加快施工速度,缩短整个建设周期。因而,采用标准设计,也是降低造价的一个方法。
4、 改变设计取费办法,实行设计质量的奖罚制度
现行的设计费计算方法,不论是按投资规模计价,还是按平方米收费,没有任何经济责任,不管工程设计的质量好坏,不论投资超不超预算,甚至不管建设项目有没有实施,设计人员有没有到现场服务,只要出了图纸,就得给设计费。这种计费办法助长了设计单位只重视技术性,忽视科学性、经济性的观念。实际工作中经常会碰到设计过于保守或设计功能没有达到最优或在施工过程中随意变更,致使工程造价居高不下和决算价大大超出原概算,对建筑业的正常发展造成不良的影响。因此,应对现行设计费的计费方法和审核办法进行改革,建立激励机制。试行在原设计计费的基础上,对因设计而节约的投资,按节约部分给予提成奖励;因设计变更而增加的投资也按增加部分扣除一定比例的设计费,实行优质优价的计费办法,这样将有利于激励设计人员精益求精地进行设计,加强设计人员的经济意识,时刻考虑如何降低造价,把控制工程造价观念渗透到各项设计和施工技术措施之中。
5、 实施限额设计:
所谓限额设计,就是按照批准的设计任务书和投资估算来控制初步设计,按照批准的初步设计总概算控制施工图设计,同时各专业在保证达到使用功能的前提下,按分配的投资限额控制设计,严格控制技术和施工图设计的不合理变更,保证总投资额不被突破。限额设计并不是一味地考虑节约投资,也决不是简单地将投资砍一刀,而是包含了尊重科学,尊重实际,实事求是,精心设计和保证设计科学性的实际内容。投资分解和工程量控制是实行限额设计的有效途径和主要方法。将"画了算"变为"算着画",时刻想着"笔下一条线,投资千万"。
要求设计单位在工程设计中推行限额设计。凡是能进行定量分析的设计内容,均要通过计算,将技术与经济相结合,用数据说话,在设计时应充分考虑施工的可能性和经济性,要和技术水平和管理水平相适应,要特别注意选用建筑材料或设备的经济性,盡量不用那些技术未过关、质量无保证、采购困难、运费昂贵、施工复杂或依赖进口的材料和设备;要尽量搞标准化和系列化的设计;各专业设计要遵循建筑模数、建筑标准、设计规范、技术规定等进行设计;要保证在项目设计达到使用功能的前提下,按分配的投资限额控制设计,严格控制技术设计和施工图设计的不合理变更,保证总投资额不被突破。
6、 加强施工图的审核工作。
这是我们以往工作中的薄弱环节。审核的内容不仅仅是各专业图纸的交圈,更重要的是检验设计图纸与投资决策中相关内容的吻合。由技术部门负责审核图纸的设计范围、结构水平、建筑标准等内容;由造价管理部门负责审核设计概算与施工图纸的一致性,设计概算与投资估算的协调性,如有超概算的项目,应与各部门之间全力配合,将突破投资的内容进行调整,为工程施工阶段的投资控制打下坚实的基础。
7、提高设计质量:
设计阶段是项目即将实施而未实施的阶段,为了避免施工阶段不必要的修改,避免设计洽商费用的增加,从而增加工程造价,应把设计做细、做深入。因为,设计的每一笔每一线都是需要投资来实现,所以在没有开工之前,把好设计关尤为重要,一旦设计阶段造价失控,就必将给施工阶段的造价控制将带来很大的负面影响。现在,有的业主往往为了赶周期、压低设计费,设计阶段的造价没有控制好,方案估算、设计概算没有或者有也不符合规定、质量不高,结果到施工阶段给造价控制造成困难。前面已提到设计费一般只相当于建设工程全寿命费用的百分之一以下,但对工程造价的影响度却占到百分之七十五以上。
三 结语
总之,设计阶段的造价控制虽然并不那么轻松,但它确是真正体现了事前控制的思想,确实能起到事半功倍的效果,达到花小钱办大事的目的,只有当业主(建设单位)真正把控制造价的关键阶段确立在设计阶段时,才能收到投资省、进度快、质量好的效果。通过技术比较、经济分析和效果评价,正确处理技术先进与经济合理两者之间的对立统一关系,力求在技术先进条件下的经济合理,在经济合理基础上的技术先进,把控制工程造价的观念渗透到各项设计和施工技术措施中,将工程造价控制工作推向一个新的里程碑。