长办自1956年至1966年对汉江规划进行过多次研究,并提出规划报告,最后,从尽量减少淹没、充分利用水力资源、并能较好地满足综合利用的要求、同时又能与沿江铁路建设统筹兼顾出发,推荐黄龙垭、石泉、安康、石房沟、丹江口五级开发.水电部四局石泉分局设计院于1976年提出的汉江上游干流规划选点报告,根据1967年水电部召集的有关各部委参加确定的开发原则及已开发的实际情况,推荐丹江口以上分黄金峡、石泉、喜河、安康、旬阳、蜀河、夹河七级开发.长办原提出的石房沟枢纽,当正常蓄水位236米时,总库容15亿立米,保证出力25.1万千瓦,装机容量100万千瓦,多年平均发电量34.5亿度.同时尚有防洪及改善航运条件之利,迁移人口一万余人,总投资约10亿元.现在确定的旬阳、蜀河、夹河三个水电站总库容
The CFO conducted many studies on the Hanjiang River Basin Plan from 1956 to 1966 and proposed a planning report. Finally, from minimizing submergence, making full use of hydraulic resources and meeting the requirements of comprehensive utilization well, at the same time, Railway construction to take all factors into consideration, recommended Huanglongya, Shiquan, Ankang, Shifanggou, Danjiangkou development 5. Hydropower Department of the Fourth Bureau Shiquan Branch Design Institute proposed in 1976, the upper reaches of the Hanjiang River mainstream planning point selection report, according to the Ministry of Water in 1967 called Of the relevant ministries to participate in the determination of the development of the principle and has been developed in the actual situation, recommended Danjiangkou above points Huangjinxia, Shiquan, Xihe, Ankang, Xunyang, Shuhe, Jiahe seven development. Hub, when the normal water level 236 meters, the total storage capacity of 1.5 billion cubic meters, to ensure that output of 251,000 kilowatts, installed capacity of 1 million kilowatts, the annual average generating capacity of 3.45 billion degrees. At the same time there are flood control and improve the shipping conditions of the benefit of migrants A million people, with a total investment of about 1000000000 yuan.Now confirmed Xunyang, Shuhe, Jiahe total capacity of three hydropower stations