2012年12月27日,深圳市审计局发布2012年深圳世界大学生运动会财务收支审计公告,大运会究竟花费几何?审计结果显示,截至2012年9月30日,为举办大运会共投入资金139.96亿元,而大运会收入合计为12.17亿元。审计还发现大运会存在部分项目未按规定实行集中采购,自行采购程序不规范,个别物资使用率较低等五大问题。大运中心主体育场钢结构工程原设计铸管工艺因在施工过程中无法实现,调整工艺后增加投资2000万元;部分钢铰支座通过设计复核后进行强化处理,增加返工、窝工费用544万元。对于出现的问题,审计机关已根据不同情况分别作出处理,有关部门已经介入并对涉事单位及责
On December 27, 2012, Shenzhen Bureau of Audit released the audit statement on the financial revenue and expenditure of Shenzhen Universiade 2012, how much does the Universiade cost? The audit results show that as of September 30, 2012, a total of RMB13,996 million has been invested to host the Universiade , While the Universiade total income of 12.17 billion yuan. The audit also found that the Universiade there are some items not in accordance with the provisions of centralized purchasing, procurement procedures are not standardized, the individual material utilization rate of five major issues. Grand Canal Center main stadium steel structure project of the original design of pipe casting process can not be achieved in the construction process, after adjusting the process an increase of 20 million yuan investment; part of the steel hinge support after the design review to strengthen processing, increase rework, nesting costs 544 Million. For the problems that arise, the auditing organs have separately dealt with them according to different situations and the relevant departments have already intervened and charged with the units involved and the responsibilities