时差——工序操作时间的机动性

来源 :建筑技术 | 被引量 : 0次 | 上传用户:moxigege
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
统筹法的推广与应用,把施工管理提高到了一个新的水平。本文拟就统筹法施工中工序操作时间的机动性问题进行初步探讨,希读者指正。一、计算时差工序的时差等于它的最迟必须开工时间减去最早可能开工时间;或它的最迟必须完工时间减去最早可能完工时间。为了便于阐述,举一钢构塔架的施工为例,该塔架施工工序流线图见图1,各工序 The promotion and application of the co-ordination law has brought construction management to a new level. This article intends to conduct a preliminary discussion on the maneuverability of the process operation time in the overall planning construction, and the Greek reader corrects it. First, the time difference for calculating the time difference process is equal to its latest required start time minus the earliest possible start time; or its latest required completion time minus the earliest possible completion time. For ease of explanation, consider the construction of a steel tower as an example. The streamline diagram of the tower construction process is shown in Figure 1. Each process
其他文献
“国破山河在,城春草木深。感时花溅泪,恨别鸟惊心。”国都,残破。山河,仍在。城池,留春。草木,幽深。这两句乃望中所见,寥寥几笔,便勾勒出一幅破败荒凉的景象,国家残破,河山
时间:2016年7月1日-2日地点:北京·新疆大厦邀您参加:首席人才官、人力资源总监、人力资源高级经理,以及来自企业负责员工关系、组织发展、业务伙伴、薪酬福利等职能范围的领
营销计划区别于我国传统概念上的销售计划,营销计划是以促进产品(或服务)营销为出发点而进行的一切事先筹划和规划,周期一般为一个年度。在营销计划中包含着市场环境分析、
强夯法曾于1970年在法国的坎内附近的某地区首次得到应用。从那时起,强夯法差不多已成为一项专门技术。由于在最近曾从事资料的收集,并且不断地改进这种方法,因此,强夯法目
传统的工程爆破主要采用炸药和雷管,爆炸时产生极大的振动,乱石横飞,炮烟弥漫,不宜在人烟稠密地区、工程改建扩建和城市建设等工程中采用。工业企业今后的改建、扩建任务是大
《偏心受压基础直接计算法》一文(见《冶金建筑》1979第3期,以下简称原文)讨论了B≤3米时基底面积的计算。对于多数地基基础情形而言,这个方法是适用的。但是,对于地基容许
最优化理论的建立和土建设计中逐步应用了电子计算机为结构的优化设计创造了条件。为多快好省地进行结构设计提供了广阔的前景。 目前常用的优化方法有几十种之多,土建问题
以上海医疗器械二厂制造的“70型”为代表的小型去离子水交換器,体积小,重量轻,出水量较大,使用方便,很适合于小型实验室、野外工作,农村四级科技网及基层医疗卫生单位使用
近几年中考文言诗文阅读题呈稳中有变的趋势,“变”的部分主要是选用课外文言诗文越来越多,开放性试题所占比重上升且形式多样。 In recent years, the reading of classica
对宁南山区典型区域——彭阳中庄小流域3种不同植被类型的土壤物理和化学性质进行了分析测定。结果表明:(1)沙棘林地和人工草地的土壤含水量、土壤容重和土壤孔隙度均小于自