阳谷修防段虽是个新建单位,但一九六四年冬修中却打了硬仗:在雨多、土湿、路难走等困难条件下,完成下方土四十九万多立方米(参加施工的人员达一万五千多人),完成任务之大,是北金堤历年冬修所没有的;施工人员之多,也为北金堤历年冬修所罕见。特别是施工中,重视了安全卫生工作,加强了领导,在整个工期却没有出现重大工伤事故,实现了安全施工的要求。健全组织加强领导为了认真贯彻上级关于安全卫生工作的指示,切
Although Yanggu repair section is a new unit, but in winter repair 1964 but played a tough battle: in the rain, soil wet, hard to walk and other difficult conditions, to complete the bottom of more than 490,000 cubic meters ( More than 15,000 people participated in the construction). The great task of accomplishing the task was not found in the winter repair of Beijiao embankments. The large number of construction workers was also rare in the winter repair of Beijiao embankments. Especially in the construction, attention was given to safety and health work, strengthened leadership, and no major industrial accidents occurred during the whole construction period, thus realizing the requirements of safety construction. Improve the organization and strengthen leadership In order to conscientiously implement the higher level on safety and health instructions, cut