飞来峡水利枢纽工程,位于北江干流清远县境内,设计正常蓄水位24.0m(珠基)。按规范,移民搬迁采用20年一遇洪水回水加发电回水外包线,土地淹没采用5年一遇洪水回水加发电回水之外包线。据此标准,初步计算淹没搬迁人口2.3万多人,淹没影响人口1.1万人。这3万多群众的安置问题,是工程规划中必须认真考虑的。也是一个十分重要和复杂的问题。因此回顾一下广东水库移民历史是有意义的。
Feilaixia Water Conservancy Project, located in the mainstream of the North River in Qingyuan County, the design of normal water level of 24.0m (bead base). According to the regulation, the resettlement relocates 20-year flood backwater plus power generation backwater outsourcing line, and the land submerged uses 5-year flood backwater plus power backwater outsourcing line. According to this standard, a preliminary calculation of flooding relocated population of more than 23,000 people, flood affected population of 11,000 people. The resettlement of more than 30,000 people must be seriously considered in the project planning. It is also a very important and complex issue. Therefore, it is meaningful to review the history of Guangdong reservoir resettlement.