湖南镇(乌溪江)水电站,装有4台4.25万千瓦的水轮发电机组,总容量为17万千瓦。机电安装工作于1979年第一季度全面展开,至9月底两台机组和110千伏开关站安装完毕交付运行;1980年另两台机组和220千伏开关站先后投产。上述机组及有关设备,由于种种原因,在制造上存在许多严重缺陷,给确保安装
Hunan (Wuxijiang) hydropower station, equipped with 4 sets of 42,500 kilowatts of hydro-generating units, a total capacity of 170,000 kilowatts. In the first quarter of 1979, the electromechanical installation work was carried out in full swing. By the end of September, both units and the 110-kilovolt switch station were installed and delivered for operation. In 1980, the other two units and the 220-kilovolt switch station were successively put into operation. The above units and related equipment, due to various reasons, there are many serious manufacturing defects, to ensure that the installation