摘 要:渠道防渗工程受复杂的坏境条件影响和各种外力作用,基状态随时都在变化,如设计、施工不够完善或管理运用不当,很容易出现病害。而管理运用中如不及时维修,则病害必将逐渐发展,影响渠道防渗工程的安全运行,严重者甚至会导致失事。实践表明,有些渠道虽然原来属于病险工程,但由于管理得当,及时采取了妥善的维修措施,因而保证了工程的正常运行。因此,为确保工程的安全和完整,充分发挥并扩大工程效益,延长工程使用寿命,必须加强管理,及时认真做好维修工作。
关键词:混凝土防渗渠道;裂缝修补;损坏修补;翻修
Abstract: canal seepage complex bad environment conditions and a variety of external force, base state at any time to change, such as design, construction, inadequate or improper use of management, it is prone to the disease. Management, utilization, if not timely maintenance, the disease will gradually develop, the safe operation of the impact of canal seepage, severe cases may even lead to the crash. The practice shows that some channels, although the original is a dangerous work, but properly managed, time to take a proper maintenance measures, thus ensuring the normal operation of the project. Therefore, in order to ensure the security and integrity of the project, give full play to expand the project benefits, extend the life of the project, we must strengthen management, to do a good job of maintenance work in a timely manner.
Keywords: concrete seepage channels; crack repair; damage repair; renovated
1.现浇混凝土防渗层的裂缝修补
当混凝土防渗层裂缝后,仍大致平整,无较大错位时,如缝宽小,可用过氯乙烯胶液涂料粘贴玻璃丝布的方法,进行修。如缝宽较大,可采用填筑伸缩缝的方法修补。对缝宽较大的型渠道,可用下列填塞与粘贴相结合的方法修补
1.1清除缝内、缝壁及缝口两边的泥土、杂物,使清洁、干燥。
1.2缝壁涂刷冷底子油。
1.3将煤焦油沥青填料或焦油塑料胶泥填入缝内,填压密实,使表面平整光滑。
1.4填好缝1~2天后,沿缝口两边各宽5cm涂刷过氯乙烯涂料一层,随即沿缝口两边各宽3~4cm粘贴玻璃丝布一层,再涂刷涂料层,贴第二层玻璃丝布,最后涂一层涂料即完成。涂料要涂刷均匀,玻璃丝布要粘平贴紧,不能有气泡。
2.预制混凝土防渗层砌筑缝的修补
预制混凝土板的砌筑缝,多是水泥砂浆缝,容易出现开裂、掉块等病害,如下及时修补不仅加大渗漏损失,而且将逐渐加重病害,造成更大损失。修补方法是:凿除缝内水泥砂浆块,将缝壁、缝口冲洗干净,用于混凝土板同标号的水泥砂浆填塞,捣实抹平后,保湿养护不得少14天。
3.混凝土防渗板表层损坏,如剥蚀、孔洞等,可采用水泥砂浆或预缩砂浆修补,必要时还可采用喷浆法修补。
3.1水泥砂浆修补
首先必须全部除掉已损坏的混凝土,并对修补部位进行凿毛处理,冲洗干净,然后在工作面保持湿润状态的情况下,将拌和好的砂浆用木抹抹到修补部位,反复压平,用铁抹抹光后,保湿养护不小于14天。当修补部位深度较大时,可在水泥砂浆中掺适量砾料,以减少砂浆干缩和增强砂浆强度。
3.2预缩砂浆修补
预缩砂浆是经拌合好之后再归堆放置30~90min才使用干哽性砂浆。当修补面积较小时,如无特殊要求,应优先采用。
拌制方法是:先将按配比(1:2或1:2.5)称量好的砂、水泥混合拌匀,再掺入加气剂的水溶液翻拌3~4次(此时砂浆仍为松散体,不是塑性状态),归堆放置30~90min,使其预先收缩后,即能使用。
水灰比(一般为0.32或0.34)应根据天气阴晴、气温高低、通风情况等因素适当调整。现场鉴定砂浆含水量多少的方法,是用手能将砂浆握成团状,手上有潮湿而又无水折出为准。由于加水量少,要注意水分均匀分布,防止阳光照射,避免出现干斑而降低砂浆质量。
修补是,先将修补部位的损坏混凝土清除,进行凿毛。冲先干净后,再涂一层厚1mm的水泥浆(水灰比为0.45~0.50),然后填入预缩砂浆,并用木锤捣实,直至表面出现少量浆液为止,最后用铁抹反复压平抹光,并盖湿草袋、洒水养护。
3.3喷浆修补
喷浆修补是将水泥、砂和水的混合料,经高压通过喷头喷射至修补部位。目前多用干料法喷浆修补。
4.混凝土防渗层的翻修
混凝土防渗层损坏严重,如破碎、错位、滑坍等,应拆除损坏部位,处理好土基土,重新砌筑。砌筑时要特别注意将新旧混凝土的接合面处理好。接合面凿毛冲洗后,需涂一层厚1mm的水泥净浆,才能开始砌筑混凝土,要注意保湿养护。
翻修中拆除的混凝土要尽量利用。如现?板能用的部分,可以不拆除;预制板能用的,尽量重新使用;破碎了的混凝土,能用的石子,也可作混凝土骨料用等。
关键词:混凝土防渗渠道;裂缝修补;损坏修补;翻修
Abstract: canal seepage complex bad environment conditions and a variety of external force, base state at any time to change, such as design, construction, inadequate or improper use of management, it is prone to the disease. Management, utilization, if not timely maintenance, the disease will gradually develop, the safe operation of the impact of canal seepage, severe cases may even lead to the crash. The practice shows that some channels, although the original is a dangerous work, but properly managed, time to take a proper maintenance measures, thus ensuring the normal operation of the project. Therefore, in order to ensure the security and integrity of the project, give full play to expand the project benefits, extend the life of the project, we must strengthen management, to do a good job of maintenance work in a timely manner.
Keywords: concrete seepage channels; crack repair; damage repair; renovated
1.现浇混凝土防渗层的裂缝修补
当混凝土防渗层裂缝后,仍大致平整,无较大错位时,如缝宽小,可用过氯乙烯胶液涂料粘贴玻璃丝布的方法,进行修。如缝宽较大,可采用填筑伸缩缝的方法修补。对缝宽较大的型渠道,可用下列填塞与粘贴相结合的方法修补
1.1清除缝内、缝壁及缝口两边的泥土、杂物,使清洁、干燥。
1.2缝壁涂刷冷底子油。
1.3将煤焦油沥青填料或焦油塑料胶泥填入缝内,填压密实,使表面平整光滑。
1.4填好缝1~2天后,沿缝口两边各宽5cm涂刷过氯乙烯涂料一层,随即沿缝口两边各宽3~4cm粘贴玻璃丝布一层,再涂刷涂料层,贴第二层玻璃丝布,最后涂一层涂料即完成。涂料要涂刷均匀,玻璃丝布要粘平贴紧,不能有气泡。
2.预制混凝土防渗层砌筑缝的修补
预制混凝土板的砌筑缝,多是水泥砂浆缝,容易出现开裂、掉块等病害,如下及时修补不仅加大渗漏损失,而且将逐渐加重病害,造成更大损失。修补方法是:凿除缝内水泥砂浆块,将缝壁、缝口冲洗干净,用于混凝土板同标号的水泥砂浆填塞,捣实抹平后,保湿养护不得少14天。
3.混凝土防渗板表层损坏,如剥蚀、孔洞等,可采用水泥砂浆或预缩砂浆修补,必要时还可采用喷浆法修补。
3.1水泥砂浆修补
首先必须全部除掉已损坏的混凝土,并对修补部位进行凿毛处理,冲洗干净,然后在工作面保持湿润状态的情况下,将拌和好的砂浆用木抹抹到修补部位,反复压平,用铁抹抹光后,保湿养护不小于14天。当修补部位深度较大时,可在水泥砂浆中掺适量砾料,以减少砂浆干缩和增强砂浆强度。
3.2预缩砂浆修补
预缩砂浆是经拌合好之后再归堆放置30~90min才使用干哽性砂浆。当修补面积较小时,如无特殊要求,应优先采用。
拌制方法是:先将按配比(1:2或1:2.5)称量好的砂、水泥混合拌匀,再掺入加气剂的水溶液翻拌3~4次(此时砂浆仍为松散体,不是塑性状态),归堆放置30~90min,使其预先收缩后,即能使用。
水灰比(一般为0.32或0.34)应根据天气阴晴、气温高低、通风情况等因素适当调整。现场鉴定砂浆含水量多少的方法,是用手能将砂浆握成团状,手上有潮湿而又无水折出为准。由于加水量少,要注意水分均匀分布,防止阳光照射,避免出现干斑而降低砂浆质量。
修补是,先将修补部位的损坏混凝土清除,进行凿毛。冲先干净后,再涂一层厚1mm的水泥浆(水灰比为0.45~0.50),然后填入预缩砂浆,并用木锤捣实,直至表面出现少量浆液为止,最后用铁抹反复压平抹光,并盖湿草袋、洒水养护。
3.3喷浆修补
喷浆修补是将水泥、砂和水的混合料,经高压通过喷头喷射至修补部位。目前多用干料法喷浆修补。
4.混凝土防渗层的翻修
混凝土防渗层损坏严重,如破碎、错位、滑坍等,应拆除损坏部位,处理好土基土,重新砌筑。砌筑时要特别注意将新旧混凝土的接合面处理好。接合面凿毛冲洗后,需涂一层厚1mm的水泥净浆,才能开始砌筑混凝土,要注意保湿养护。
翻修中拆除的混凝土要尽量利用。如现?板能用的部分,可以不拆除;预制板能用的,尽量重新使用;破碎了的混凝土,能用的石子,也可作混凝土骨料用等。