论文部分内容阅读
海湾及潮汐河口的冷却水工程研究近年来普遍受到人们的重视.由于受潮汐影响,其冷却水工程布置及热污染特性较之河道及水库型工程更为复杂.本文以新会电厂为例,详细说明潮汐河道冷却水工程试验研究方法及其排取水口布置形式,对多种布置方案进行对比试验和优劣分析,最终提出合理排取水口布置形式,且给出了电厂取水温升和热污染范围,为设计及环评工作提供了依据.关
In recent years, research on cooling water engineering in the Gulf and tidal estuaries has drawn people’s attention. Due to tides, the cooling water engineering layout and thermal pollution characteristics are more complicated than that of river courses and reservoir type projects. Taking Xinhui Power Plant as an example, this paper describes in detail the experimental research methods of tidal river cooling water project and the layout of discharge outlets, compares and tests the advantages and disadvantages of various layouts, and finally puts forward the layout of discharge outlets rationally Out of the power plant water temperature rise and thermal pollution range, the design and the EIA work provided the basis. turn off