论文部分内容阅读
在公和斜拉桥1号桥墩承台大体积混凝土冬季施工中,通过原材料选用、配合比设计、混凝土内部温度控制措施,保证了工程质量。
In the winter construction of the mass concrete of the pier and the bridge pier of No. 1 of Gonghe Cable Stayed Bridge, the quality of the project is ensured through the raw material selection, mix design and concrete internal temperature control measures.