2007年“天光一号”加速器检修工作从2007年11月19日开始,至2007年12月27日结束,历时30个工作日。检修的内容包括:1)实验室地线改造;2)检修冷却循环水系统;3)检修气系统和排气系统;4)检修高纯水循环系统;5)检修加速控制系统;6)检修水处理系统;7)检修油处理系统;8)检修主开关激光注入系统;9)检查二极管阴、阳极和主膜;10)检修主放二极管均压环;11)检查Marx发生器;12)实验室工作环境整理,加速器备品备件整理,实验室辅助部件重新排布。
2007 “Tiangong One ” accelerator overhaul work from November 19, 2007 onwards, to December 27, 2007 ended, which lasted 30 working days. The overhaul includes: 1) ground modification of laboratory; 2) overhaul of cooling circulating water system; 3) overhaul gas system and exhaust system; 4) overhaul of high purity water circulation system; 5) overhaul acceleration control system; System; 7) overhaul oil treatment system; 8) overhaul main switch laser injection system; 9) check the anode and cathode of the diode and the main membrane; 10) overhaul main amplifier diode grading ring; 11) check Marx generator; Work environment, accelerator spare parts sorting, laboratory aided re-arrangement of accessories.