论文部分内容阅读
通过在郑西铁路客运专线桥梁桩基施工中的具体验证,结合钻孔灌注桩在施工过程中出现的问题,对钻孔桩关注的施工技术进行了阐述,针对施工过程中出现事故的原因进行了分析,并提出了相应的预防及处理措施。
Through the concrete verification of the bridge pile foundation construction in Zhengzhou-Xi’an Railway Passenger Dedicated Line and the problems in the construction process of the bored piles, the construction techniques concerned with the bored pile are expounded. In view of the reasons of the accidents in the construction process Analysis, and put forward the corresponding prevention and treatment measures.