02省道临安至昌化一级公路改建工程为浙江省重点建设项目,也是省人民政府批准的“四自”工程。工程起自玲珑镇、藻溪镇、於潜镇、太阳镇,终至昌化镇,全长46.9公里,按山岭重丘一级公路标准建设,双向四车道,路基宽22.5米,设计时速60公里。该工程由临安市人民政府、项目业主单位共同组织实施,由临安市副市长吴苗强担任工程总指挥。02省道临安至昌化段改建工程于1999年元月1日动工,2001年7月1日完工,总投资4.5亿元。整
02 provincial highway Lin’an to Changhua a highway reconstruction project for key construction projects in Zhejiang Province, is also the provincial people’s government approved “four from ” project. The project starts from Delicate Town, Algae Town, Yuqian Town, Taiyang Town, and finally Changhua Town, with a total length of 46.9 kilometers. It is built according to the standard of a mountainous heavy hilly highway with a two-way four-lane roadbed 22.5 meters wide and a designed speed of 60 Km. The project is jointly implemented by the People’s Government of Lin’an City and the project owner. Wu Miaokiang, vice mayor of Lin’an City, is the general commander of the project. 02 Provincial Highway Lin’an to Changhua Section reconstruction project started on January 1, 1999, completed on July 1, 2001 with a total investment of 450 million yuan. whole