记者:农网改造进展如何? 原固均副主任:全国农村电网改造工程98、99两年总共下达资金1852亿元,到目前为止,也就是五月底,已完成406个县的电网改造工程,按工程总投资计算,累计已完成了总量的75%,也就是说,四分工程已搞定三分,可以说,取得了阶段性的成果。 在农网改造过程中,我们提出了三个要求,第一、不出质量问题;第二、不出资金问题;第三、不出安全问题。所谓不出质量问题,就是在改造过程中,不允许出现豆腐渣工程、胡子工程;所谓不出资
Reporter: How is the progress of the rural grid transformation? Former Deputy Governor Gu, Deputy: In the 98, 99 years of the National Rural Power Grid Renovation Project, a total of 185.2 billion yuan was allocated for funds. Up to the end of May, 406 counties have completed power grid reconstruction projects. Calculated according to the total project investment, the cumulative total has completed 75% of the total, that is, four-point project has been set to three points, it can be said that achieved phased results. In the process of rural power grid transformation, we put forward three requirements. First, there is no quality problem. Second, there is no capital issue. Third, no security issue. The so-called “no quality problem” means that during the renovation process, the rubbish project and the beard project will not be allowed; so-called non-funded projects